LATESTChile to cut diesel by 142 pesos a litre and freeze fuel prices until MarchTotalEnergies withdraws H2 Magallanes, the US$16 billion green hydrogen project in ChileGrenergy asks Chile's grid operator to lift the 15% cap on eight solar PMGD plants, saying the fault tripped themBrookfield buys a majority stake in Chile's Verano Energy, which plans US$1.6 billion for 2.5 GW of solar and batteries
ENERGÍA FUTURA
Solar Energy

Chile has 3,850 MW of generation under construction and US$11.125 billion in environmental review

By ·

Chile has 3,850 MW of generation under construction and US$11.125 billion in environmental review

Generation projects under construction on Chile's National Electric System total 3,850 MW across 173 projects, and another 47 projects with 7,674 MW are awaiting environmental approval, with estimated investment of US$11.125 billion. The figures, which exclude batteries, come from the September 2026 bulletin of Generadoras de Chile, compiled with data from the National Energy Commission (CNE) and reported on 12 November by Electrominería.

Adding storage systems, capacity under construction reaches 9,213 MW in 256 projects, 97.2% of it renewable. Batteries, with 5,346 MW, already account for 58% of everything being built for the power system.

Chile's power generation pipeline as of September 2026
3,850 MWUnder construction (excl. batteries)173 projects
9,213 MWUnder construction incl. batteries256 projects; 97.2% renewable
7,674 MWIn environmental review47 projects, excl. batteries
US$11,125 MInvestment under reviewMillions of dollars
View the data as a table
Under construction (excl. batteries)3,850 MW
Under construction incl. batteries9,213 MW
In environmental review7,674 MW
Investment under reviewUS$11,125 M

Generation projects under construction, by technology

Solar PV dominates comfortably: 3,023 MW in 144 projects, plus 17 MW from three hybrid plants with batteries. Next come wind, with 346 MW in 12 projects; run-of-river hydro, with 221 MW in 10 projects; and thermal, with 260 MW in seven plants, almost all diesel-fired backup units (257 MW) plus a small gas plant (3 MW).

Solar's weight explains why the power debate is shifting toward night-time supply and transmission: every new PV plant adds energy at midday, when the north already has a surplus. That is why batteries, which shift that energy into the night, are growing even faster than generation, as our story on 11.3 GW of storage across operation, testing and construction shows.

Solar dominates generation under constructionMW under construction by technology, excl. batteries, September 2026
View the data as a table
Solar PV3,040 MW · 144 projects (3,023 MW) + 17 MW from 3 battery hybrids
Wind346 MW · 12 projects
Thermal260 MW · 7 projects (257 MW diesel, 3 MW gas)
Run-of-river hydro221 MW · 10 projects
TechnologyCapacity under construction (MW)Projects% of total incl. batteries
Batteries (BESS)5,3468058.0%
Solar PV3,02314432.8%
Wind346123.8%
Thermal (diesel and gas)26072.8%
Run-of-river hydro221102.4%
Solar with batteries (solar component)1730.2%
Total9,213256100%

Source: Generadoras de Chile, September 2026 bulletin, capacity under construction, with CNE data. Excluding batteries, the total is 3,850 MW in 173 projects.

Construction works on the wall of the Angostura hydroelectric plant, with machinery and containers
Works at the Angostura hydroelectric plant on the Biobío river during construction. Today 221 MW of run-of-river hydro plants are being built in Chile. Photo: Marcelo A. Contreras / Wikimedia Commons (CC BY-SA 3.0).

Where the projects under construction are

Including batteries, the three northernmost mining regions account for more than half of the works: Antofagasta has 2,006 MW, Atacama 1,953 MW and Tarapacá 1,647 MW. Further south, Coquimbo (751 MW), Maule (699 MW) and Biobío (564 MW) stand out. The environmental pipeline is also large in the Atacama Region, as we showed when reviewing the US$7.325 billion under review there.

Where Chile's new power capacity is being builtMW under construction by region, including batteries, September 2026
12 MW50 MW250 MW700 MW1,500 MW–2,006 MW
Arica y Parinacota12 MW
Tarapacá1,647 MW
Antofagasta2,006 MW
Atacama1,953 MW
Coquimbo751 MW
Valparaíso227 MW
Metropolitana309 MW
O'Higgins415 MW
Maule699 MW
Ñuble219 MW
Biobío564 MW
La Araucanía48 MW
Los Ríos188 MW
Los Lagos152 MW
View the data as a table
Antofagasta2,006 MW
Atacama1,953 MW
Tarapacá1,647 MW
Coquimbo751 MW
Maule699 MW
Biobío564 MW
O'Higgins415 MW
Metropolitana309 MW
Valparaíso227 MW
Ñuble219 MW
Los Ríos188 MW
Los Lagos152 MW
La Araucanía48 MW
Arica y Parinacota12 MW

What is in environmental review

The Environmental Impact Assessment System holds 47 generation projects with 7,674 MW and US$11.125 billion, excluding batteries. Solar PV leads with 3,985 MW in 34 projects and US$5.262 billion; wind adds 1,934 MW in 10 projects and US$3.754 billion, and two solar-wind hybrid projects account for 1,695 MW and US$2.05 billion. A 60 MW diesel plant completes the list.

What is in environmental review and how much it costsInvestment in US$ million by technology (and MW), excl. batteries
View the data as a table
Solar PVUS$5,262 · 3,985 MW in 34 projects
WindUS$3,754 · 1,934 MW in 10 projects
Solar + wind hybridsUS$2,050 · 1,695 MW in 2 projects
Thermal (diesel)US$59 · 60 MW in 1 project
TechnologyCapacity (MW)ProjectsInvestment (US$ million)
Solar PV3,985345,262
Wind1,934103,754
Solar + wind hybrid1,69522,050
Thermal (diesel)60159
Total excl. batteries7,6744711,125
Batteries (BESS)2519587
Total incl. batteries7,9255611,712

Source: Generadoras de Chile, September 2026 bulletin, capacity in environmental review, with CNE data to August 2026.

By region, capacity under review is concentrated in Antofagasta (2,299 MW), Atacama (1,390 MW) and Los Lagos (1,211 MW), the latter driven by wind projects, such as the four farms we covered in our story on 1,202 MW of wind under review in Los Lagos.

Antofagasta, Atacama and Los Lagos lead capacity under reviewMW in environmental review by region, including batteries (7,925 MW), CNE data to August 2026
0 MW50 MW200 MW700 MW1,500 MW–2,299 MW
Arica y Parinacota0 MW
Tarapacá143 MW
Antofagasta2,299 MW
Atacama1,390 MW
Coquimbo329 MW
Valparaíso943 MW
Metropolitana18 MW
O'Higgins768 MW
Maule452 MW
Ñuble50 MW
Biobío107 MW
La Araucanía0 MW
Los Ríos216 MW
Los Lagos1,211 MW
View the data as a table
Antofagasta2,299 MW
Atacama1,390 MW
Los Lagos1,211 MW
Valparaíso943 MW
O'Higgins768 MW
Maule452 MW
Coquimbo329 MW
Los Ríos216 MW
Tarapacá143 MW
Biobío107 MW
Ñuble50 MW
Metropolitana18 MW
Arica y Parinacota0 MW
La Araucanía0 MW

Does your company build, finance or supply energy projects? Reach Energía Futura's readers.

See advertising options
Wind turbines of the Canela II wind farm next to Route 5 North in Coquimbo
The Canela II wind farm next to Route 5 North in Coquimbo. Wind has 346 MW under construction and 1,934 MW in environmental review. Photo: Rjcastillo / Wikimedia Commons (CC BY-SA 4.0).

Environmental approvals fall in 2026

The bulletin shows a cooling in new project entries. So far in 2026, capacity submitted for environmental review totals 2,558 MW, down 45.5% from 2025, and capacity with an approved environmental qualification resolution (RCA) reaches 3,447 MW, down 31.5%. Investment with an approved RCA, however, is up 3.5% at US$6.622 billion.

IndicatorSeptember 20262026 to dateChange vs 2025
Capacity submitted for review158.1 MW2,558 MW−45.5%
Capacity with approved RCA460.6 MW3,447 MW−31.5%
Investment with approved RCAUS$1.247 billionUS$6.622 billion+3.5%

Source: Generadoras de Chile, September 2026 bulletin, with CNE data to August 2026.

The drop in new projects comes as the system curtails solar power at midday, spot prices are very low during sunny hours and transmission is constrained in the north. At the same time, batteries already make up most of what is being built, a sign of where investment is moving.

What the construction pipeline means for the system

The 3,850 MW of generation under construction equal about a tenth of the country's installed capacity, which stands at 39,231 MW according to the same bulletin (28,027 MW renewable and 11,204 MW thermal). Since almost all of it is solar, its contribution will be concentrated in sunny hours, exactly when energy is being curtailed in the north today. That is why perhaps the most relevant figure in the bulletin is another one: for every MW of generation being built, 1.4 MW of batteries are being installed, a ratio that did not exist three years ago.

Thermal capacity under construction, meanwhile, is almost all backup: 257 MW of oil-fired plants designed to run a few hours a year at tight moments. Run-of-river hydro, with 221 MW, is the only firm renewable technology that is growing, though far more slowly than solar. In review, wind and hybrid projects add up to more than 3,600 MW, and they are the ones that could supply night-time energy once they start operating.

Frequently asked questions

How many power generation projects are being built in Chile?

173 projects with 3,850 MW, excluding batteries, as of September 2026. With the 80 storage projects, there are 256 with 9,213 MW.

Which technology leads construction?

Solar PV, with 3,023 MW in 144 projects. Counting batteries, storage is what is being built the most, with 5,346 MW.

How much investment is in environmental review?

US$11.125 billion in 47 generation projects with 7,674 MW. Including batteries, the figure rises to US$11.712 billion.

Where do these figures come from?

From the monthly bulletin of Generadoras de Chile, which processes the CNE registers of projects under construction and in environmental review.