LATESTChile to cut diesel by 142 pesos a litre and freeze fuel prices until MarchTotalEnergies withdraws H2 Magallanes, the US$16 billion green hydrogen project in ChileGrenergy asks Chile's grid operator to lift the 15% cap on eight solar PMGD plants, saying the fault tripped themBrookfield buys a majority stake in Chile's Verano Energy, which plans US$1.6 billion for 2.5 GW of solar and batteries
ENERGÍA FUTURA
Solar Energy

Grenergy asks Chile's grid operator to lift the 15% cap on eight solar PMGD plants, saying the fault tripped them

By ·

Grenergy asks Chile's grid operator to lift the 15% cap on eight solar PMGD plants, saying the fault tripped them

Spanish developer Grenergy has asked Chile's National Electricity Coordinator to revoke the order limiting to 15% of installed capacity the output of eight of its small distributed generation plants (PMGD), all solar plants in central Chile. In a letter sent on 12 November, the company argued that those plants tripped as a consequence of the fault on Sunday 8 November and were not its cause, Electrominería reported on 13 November.

The request targets the measure the Coordinator ordered on 9 November, in force since the 10th, after some 520 MW of PMGD plants disconnected within seconds in the Metropolitan, Valparaíso and O'Higgins regions. The case tests how the protections of thousands of small plants connected to distribution networks are set.

The cap Grenergy wants lifted
8Plants affectedGrenergy solar PMGD plants
15%Maximum output allowedOf installed capacity
75 msFault duration8 Nov, 220 kV line
18°Anti-islanding settingVoltage vector shift
Source: Grenergy letter to the Coordinator via Electrominería, 13 Nov 2026; locations: National Electricity Coordinator's Infotécnica
View the data as a table
Plants affected8
Maximum output allowed15%
Fault duration75 ms
Anti-islanding setting18°

Grenergy's eight PMGD plants under the cap

The plants affected are GR Alcón Solar, Santa Teresita, Chiloé, La Paz, Malloco, Argomedo, Lo Miguel and Javiera Carrera. According to the Coordinator's technical registry (Infotécnica), four are in the Metropolitan Region (Lampa, Pudahuel, Peñaflor and Buin), three in O'Higgins (Marchigüe, Quinta de Tilcoco and Rengo) and one in Maule (Curicó). Seven are listed under the GR Palmas de Cocalán group, whose name matches Palmas, Grenergy's cluster of solar PMGD plants in central Chile; Javiera Carrera is registered to GR Torres del Paine.

Where Grenergy's eight capped PMGD plants areNumber of plants by region
12345–4
Metropolitana4
O'Higgins3
Maule1
Other regions have no plants on this list.Source: Grenergy letter to the Coordinator via Electrominería, 13 Nov 2026; locations: National Electricity Coordinator's Infotécnica
View the data as a table
Plants
Metropolitana4 · Lampa, Pudahuel, Peñaflor, Buin
O'Higgins3 · Marchigüe, Quinta de Tilcoco, Rengo
Maule1 · Curicó
Grenergy's eight solar plants with capped output
GR Alcón SolarMarchigüeO'Higgins
ArgomedoQuinta de TilcocoO'Higgins
Lo MiguelRengoO'Higgins
ChiloéCuricóMaule
Santa TeresitaLampaMetropolitana
La PazPudahuelMetropolitana
MallocoPeñaflorMetropolitana
Javiera CarreraBuinMetropolitana
Source: Grenergy letter to the Coordinator via Electrominería, 13 Nov 2026; locations: National Electricity Coordinator's Infotécnica

PMGD plants are up to 9 MW and connect to distribution companies' networks rather than to transmission. Capping them at 15% means a 9 MW plant can deliver only 1.35 MW at midday, when it produces most. Grenergy did not say in its letter how much energy it has been unable to inject since 10 November, nor has the Coordinator published the total capacity of the plants included in the order.

Grenergy's argument: the PMGD anti-islanding protection worked as required

Using the oscillography records the Coordinator requested, Grenergy explained that the disconnections were caused by the voltage vector shift (VVS) protection in the reclosers that connect each plant to the distribution grid. It is an anti-islanding function: it detects sudden changes in the voltage angle and disconnects the plant so it does not keep energising a section of network that has separated from the system, which is dangerous for utility workers.

According to the company, the protection was set at 18 degrees, in line with the Technical Standard for PMGD Connection and Operation (CNE Exempt Resolution No. 69 of 2026), and reacted automatically to the fault on the transmission grid, which was cleared in about 75 milliseconds. It added that the settings were updated and verified in August by a class A electrical installer, ahead of regulatory deadlines.

PointWhat Grenergy says
Cause of the disconnectionThe voltage vector shift protection in the reclosers tripped
Protection setting18°, per the PMGD Technical Standard (CNE Res. 69/2026)
Original faultOn the transmission grid, cleared in ~75 ms
Settings verifiedAugust 2026, by a class A installer
Risk to the systemIts plants do not warrant the exceptional measures of DS 88
ProposalReview the selectivity of anti-islanding settings with the distributors

Source: Grenergy's letter to the National Electricity Coordinator of 12 November 2026, via Electrominería.

San Cristóbal electrical substation building in Recoleta, Santiago
The San Cristóbal substation in Recoleta. The 8 November fault occurred on 220 kV facilities between the Chena and Cerro Navia substations, also in Santiago. Photo: Carlos yo / Wikimedia Commons (CC BY-SA 4.0).

What the Coordinator ordered after the 8 November fault

The order relies on Supreme Decree No. 88 of 2019, the regulation for small generators, which allows exceptional measures when a plant puts the security of supply at risk. The Coordinator asked the owners of the PMGD plants named in the order to send, by 13 November, the output they had just before and after the event, the make and model of their protections, their settings and the records explaining the disconnection, as detailed in our story on the 15% cap on PMGD plants.

The Coordinator's concern has grounds: the fault pushed system frequency down to 48.93 Hz, against a nominal 50 Hz, and the 520 MW loss exceeded by about 30% the primary frequency control reserve, of roughly 400 MW, according to academics quoted by Electrominería. If many small plants switch off at once in response to a distant fault, the system suddenly loses generation it has to replace within seconds.

From the 8 November fault to Grenergy's request
  1. 8 Nov, 14:54220 kV faultBetween Chena and Cerro Navia; 520 MW of PMGD trip.
  2. 9 NovCoordinator's order15% cap on the PMGD plants that tripped.
  3. 10 NovCap takes effect
  4. 12 NovGrenergy's letterSubmits oscillography records and asks to lift the cap.
  5. 13 NovData deadline
Source: Grenergy letter to the Coordinator via Electrominería, 13 Nov 2026; locations: National Electricity Coordinator's Infotécnica
8 November faultValue
Time14:54
Facility220 kV lines between the Chena and Cerro Navia substations
Clearing time~75 milliseconds
PMGD disconnected520 MW (Metropolitan, Valparaíso and O'Higgins)
Minimum frequency48.93 Hz
Primary control reserve~400 MW

Source: National Electricity Coordinator daily report and University of Santiago academics, via Electrominería (11 and 12 November 2026).

The underlying dilemma: protecting the grid without tripping PMGD plants

The case reflects a well-known technical tension in systems with lots of distributed generation. Anti-islanding protections must be sensitive enough to cut a plant off if its section of network is isolated, but if they are too sensitive they also react to transmission disturbances that do not affect them directly. Grenergy offered to review with distributors the selectivity of those settings, so that they can tell a real island from a distant fault.

The PMGD segment totalled 3,820 MW in May 2026, according to the Chilean Renewable Energy and Storage Association (Acera), and is at the centre of a regulatory debate over new curtailment-sharing rules and its new stabilised prices set by the CNE, as we explained in our story on PMGD stabilised prices. Grenergy is also one of the country's largest solar developers: in October it closed US$457 million in financing for its Algarrobal and Palmas projects, as we reported in our story on Grenergy's financial close.

Inspection of solar panels at a photovoltaic plant
Solar panels at a photovoltaic plant in Pozo Almonte. Grenergy's PMGD plants capped at 15% are in central Chile, close to consumption centres. Photo: Ministerio de Bienes Nacionales / Wikimedia Commons (CC BY 2.0).

Does your company operate PMGD plants, protection systems or distribution grids? Reach Energía Futura's readers.

See advertising options

What comes next

The Coordinator must review the information sent by Grenergy and the other PMGD owners before deciding whether to keep, change or lift the restriction, which has no end date. It will also have to deliver its fault analysis report, which should specify how many plants disconnected, why and with what settings. Meanwhile, the eight plants keep operating under a 15% ceiling.

Frequently asked questions

What did Grenergy ask the Coordinator?

To revoke the order capping at 15% of capacity the output of eight of its solar PMGD plants, in force since 10 November 2026.

Why did the PMGD plants disconnect on 8 November?

According to Grenergy, the voltage vector shift anti-islanding protection, set at 18° under the technical standard, tripped in response to a fault on a 220 kV line in Santiago that was cleared in about 75 milliseconds.

What is a PMGD?

A small distributed generation plant: a power plant of up to 9 MW connected to a distribution company's grid. In Chile most of them are solar.

Where are the capped plants?

Four in the Metropolitan Region (Lampa, Pudahuel, Peñaflor and Buin), three in O'Higgins (Marchigüe, Quinta de Tilcoco and Rengo) and one in Maule (Curicó), according to the Coordinator's registry.