El Valle solar park: Trinergy files 139 MW with batteries in La Estrella, Chile, for US$190 million

By ·

El Valle solar park: Trinergy files 139 MW with batteries in La Estrella, Chile, for US$190 million

The El Valle solar park has entered environmental review. El Valle SpA, a subsidiary of developer Trinergy, filed an Environmental Impact Statement (DIA) with Chile's environmental assessment system (SEIA) to build a photovoltaic plant with battery storage in the district of La Estrella, in the O'Higgins region, with an investment of US$190 million, Revista Electricidad reported on 27 November 2026.

The project, officially named «Parque Solar El Valle y Línea de Transmisión 1×110 kV», will have 340,140 bifacial modules of 620 Wp or similar and a nominal output of 139 MW at the connection point, the La Estrella 110 kV substation. It will cover 310.9 hectares and include a battery energy storage system (BESS) with 168 storage modules and 42 transformer stations.

El Valle in four figures
139 MWOutput at the connection pointLa Estrella 110 kV substation
US$190 millionInvestment
340,140Bifacial modules620 Wp or similar
310.9 haArea
Source: Revista Electricidad, 27 November 2026, based on the SEIA filing
View the data as a table
Output at the connection point139 MW
InvestmentUS$190 million
Bifacial modules340,140
Area310.9 ha

What the El Valle solar park is

The plant will generate electricity from the sun and store part of the midday output in its batteries to deliver it later to the National Electric System (SEN), when solar generation drops. It is the design now repeated in almost every new project in central and northern Chile, because midday solar power is paid less and less, while afternoon and night-time power is paid more and more.

To export its power, the project will build a 6.7-kilometre, 110 kV line: about six kilometres overhead, on 36 structures, and the last 700 metres underground. According to Revista Electricidad's report, the filing does not state the battery capacity in megawatt-hours, the figure that defines how many hours of energy it can deliver.

FeatureEl Valle solar park
OwnerEl Valle SpA (Trinergy subsidiary)
InvestmentUS$190 million
District and regionLa Estrella, O'Higgins region
Modules340,140 bifacial, 620 Wp or similar
Output at connection point139 MW
Area310.9 hectares
Batteries168 modules and 42 transformer stations (MWh not disclosed)
Connection110 kV, 6.7 km line to La Estrella substation
Filing typeDIA (environmental impact statement)
Planned start of worksOctober 2028
Useful life32 years and 8 months

Source: Revista Electricidad, 27 November 2026, based on the DIA filed with the SEIA. The project's SEIA record could not be checked directly at the time of writing.

Rodeo arena in La Estrella, O'Higgins region, with wooden stands
The rodeo arena in La Estrella, the rural district in Cardenal Caro province where the El Valle solar park would be built. Photo: Enefau / Wikimedia Commons (CC BY-SA 3.0).

Jobs and timeline of the El Valle solar park

According to the filing, construction would employ an average of 400 workers, peaking at 650. Operation would employ an average of 19 people (peak 25) and decommissioning an average of 50, peaking at 120. Works are scheduled to begin in October 2028 and the estimated useful life is 32 years and eight months.

Up to 650 people during construction and 25 in operationExpected peak workforce by phase
Source: Revista Electricidad, 27 November 2026, based on the SEIA filing
View the data as a table
Construction650 · Average: 400
Decommissioning120 · Average: 50
Operation25 · Average: 19

The long timeline is by design. An impact statement takes on average more than a year to be resolved: Chile's Environmental Assessment Service acknowledged an average of 399 days for DIAs in 2025, as we reported in the SEA plan to cut review times by 30%. Grid connection and equipment procurement come on top of that.

El Valle solar park timeline
  1. November 2026Enters environmental review (DIA)
  2. October 2028Planned start of works
  3. 32 years 8 monthsEstimated useful life
Source: Revista Electricidad, 27 November 2026, based on the SEIA filing

O'Higgins, a region adding batteries

El Valle is not alone. In 2026 the O'Higgins region has received several solar or storage projects. In May, Spain's Ríos Renovables filed a 240 MWh BESS in Peumo for US$55.3 million; in July, PLAN 8 filed the Las Quintas hybrid park (wind, solar and batteries) between San Pedro and Litueche for US$200 million; and in August the regional commission approved Grenergy's Elara BESS in Rengo, 90 MW and 540 MWh, for US$123.3 million.

ProjectOwnerDistrictTypeInvestmentStatus in 2026
Las QuintasPLAN 8San Pedro (Santiago region) and LituecheWind + solar + BESSUS$200 millionEIA filed in July
El ValleTrinergyLa EstrellaSolar + BESSUS$190 millionDIA filed in November
ElaraGrenergyRengoBESS 90 MW / 540 MWhUS$123.3 millionApproved in August
Ríos de PedrazaRíos RenovablesPeumoBESS 240 MWhUS$55.3 millionDIA filed in May
AucanquilchaBIWOMarchigüeBESS 40 MW / 200 MWhUS$45 millionApproved in November

Source: Revista Electricidad (May, July, August and November 2026) and Energía Futura. Amounts declared by the owners; they are not investments already made.

El Valle joins other battery projects in O'HigginsSolar or storage projects in the region in 2026; value = investment in US$ million
Las Quintas (PLAN 8), LituecheWind + solar + BESS · EIA Jul 2026
El Valle (Trinergy), La Estrella139 MW + BESS · filed Nov 2026
Ríos de Pedraza, PeumoBESS 240 MWh · filed May 2026
Elara (Grenergy), RengoBESS 90 MW / 540 MWh · approved Aug 2026
Reference location in each project's district. Las Quintas spans San Pedro (Santiago region) and Litueche.Source: Revista Electricidad: El Valle, Ríos de Pedraza, Elara and Las Quintas
View the data as a table
El Valle (Trinergy), La Estrella139 MW + BESS · filed Nov 2026
Las Quintas (PLAN 8), LituecheWind + solar + BESS · EIA Jul 2026
Elara (Grenergy), RengoBESS 90 MW / 540 MWh · approved Aug 2026
Ríos de Pedraza, PeumoBESS 240 MWh · filed May 2026
El Valle is among the largest battery projects in O'Higgins this yearDeclared investment, US$ million
Source: Revista Electricidad: El Valle, Ríos de Pedraza, Elara and Las Quintas
View the data as a table
Las QuintasUS$200.0
El ValleUS$190.0
ElaraUS$123.3
Ríos de PedrazaUS$55.3

The region has an advantage: it is close to the large consumption centres of central Chile, where grid congestion is lower than in the north, home to most of the country's solar power. The closest case is the Marchigüe batteries, approved this month about 20 kilometres from La Estrella.

Litueche square with palm trees and a solar street lamp
The main square of Litueche, the district next to La Estrella where the Las Quintas hybrid park is also planned. Photo: Marco Antonio Correa Flores / Wikimedia Commons (CC BY-SA 4.0).

Why new solar projects come with batteries

Chile already has more solar power than its grid can use at midday. During sunny hours the marginal cost falls to zero and part of the output is curtailed. Batteries shift that energy to the afternoon and night, when the system still relies on gas and coal plants and on hydro reservoirs.

That is why almost every solar park filed with the SEIA includes storage, and many projects are batteries only. Financing is following: in the same region, Verano Energy secured US$187 million for Observatorio, a solar plant with a 600 MWh battery in Marchigüe. Five years ago Chile had almost no grid-scale batteries in operation.

  • Filing: DIA in November 2026; admission and review follow, with possible queries (Icsara) from public agencies.
  • Missing figure: battery capacity in MWh, not disclosed in the press report.
  • Works: from October 2028, if it obtains its environmental approval and sector permits.
  • Connection: depends on the 6.7 km, 110 kV line to La Estrella substation.

Does your company build, finance or supply solar-plus-storage parks? Reach Energía Futura's readers.

See advertising options

Frequently asked questions

What is the El Valle solar park?

It is a photovoltaic plant with 139 MW at the connection point and a battery system that Trinergy plans in La Estrella, O'Higgins region, for US$190 million.

Has it been approved?

No. It was filed as an environmental impact statement in November 2026 and must go through admission and review.

When would it be built?

The owner plans to start works in October 2028, with up to 650 workers during construction.

How much energy will the batteries store?

Published information mentions 168 storage modules but does not state capacity in MWh.