Chile's Environmental Assessment Service (SEA) has set a goal of cutting environmental review times by 30% for investment projects between 2026 and 2030, “without reducing rigour or environmental standards”. The plan, called the Efficiency and Technical Excellence Plan for Environmental Assessment 2026-2030, was presented to the agency's Civil Society Council (COSOC) in an online session on Thursday 19 November, according to a statement published by the SEA on 23 November.
The starting point is high. In 2025, an Environmental Impact Declaration (DIA) took on average 399 days to get its ruling and an Environmental Impact Study (EIA) 1,124 days, more than three years, according to the SEA's annual public account. The legal limits are 60 and 120 working days respectively, although they can be extended and suspended.
View the data as a table
| Target cut in review times | 30% |
| Average DIA in 2025 | 399 days |
| Average EIA in 2025 | 1,124 days |
| Tovaku's review | 450 days |
What the 2026-2030 environmental review plan proposes
The SEA's executive director, Arturo Farías, led the session, and the head of the Environmental Assessment and Public Participation Division, Rodrigo Román, presented the plan. The agency's diagnosis is that total processing times for DIAs and EIAs “have risen steadily over the past decade”. Five measures were announced:
- Streamline processes to focus work on the technical review of projects.
- Monitor evaluators' workload and track case files.
- Standardise public participation and indigenous consultation processes.
- Train environmental assessment staff.
- Support the work with artificial intelligence tools, mainly to automate administrative tasks.
Council members such as María Elisa Quinteros (Council of Rectors), Alejandro Buschmann (Chilean Academy of Sciences), Ramón Balcázar (Fundación Tantí) and Diego Rojas (Fundación Terram) raised questions about the plan. The SEA did not publish yearly milestones or what meeting the 30% target would mean in days.

How long an environmental review takes today
The SEA's public account shows that over the past ten years the average for DIAs ranged between 295 and 499 days, and for EIAs between 731 and 1,124 days. If the 30% target were applied to 2025 averages, a DIA would fall to about 279 days and an EIA to about 787 days. That calculation is Energía Futura's: the SEA only gave a percentage.
| Type of filing | Legal limit | Actual 2025 average | 30% lower (calculation) |
|---|---|---|---|
| Environmental Impact Declaration (DIA) | 60 working days | 399 days | 279 days |
| Environmental Impact Study (EIA) | 120 working days | 1,124 days | 787 days |
Source: SEA public account, July 2026, via Reporte Minero. Averages are calendar days from filing to ruling and include suspensions requested by developers, which is why they far exceed the legal limit. Other measurements, such as Sofofa's Prisma, use different cut-offs and give somewhat different figures.
There are signs times can be shortened. The Tovaku mining project, worth US$870 million, with its own solar park and seawater supply, was reviewed in 450 days, “about 55% less than the average” for EIAs ruled on in 2025 and the fastest review of a project above US$500 million since 2018, according to the October approvals report. We covered it in our story on Tovaku's approval.
Mining and energy, the most exposed to review times
In July 2026 there were 373 projects under review worth US$99,793 million. Mining (US$30,659 million) and energy (US$25,105 million) made up more than half. By region, Magallanes led with US$31,818 million, the region where green hydrogen projects are concentrated, followed by Antofagasta with US$28,981 million.
The government had already bet on fast-tracking permits for projects it sees as key: early in its term it picked 20 strategic energy projects to shorten their processing. And approvals have sped up: between 11 March and late July, the SEA approved 117 projects worth US$19,871 million.
The filings chart shows a change of scale: in this administration's first months, 128 projects worth US$37,924 million were submitted, fewer than half as many as in 2014 but more than three times the investment. That means more complex reviews, with more comments from public agencies and more public participation, exactly what the plan aims to organise.

What was approved in October
In October 2026 the SEA ruled on 27 projects and approved 26, worth US$2,624.5 million. There were 24 DIAs and 2 EIAs (Tovaku in Antofagasta and the Ceibo solar park in Atacama). Energy projects approved include the Elena 2 PV park (US$577 million), Ceibo (US$220 million), Hemera (US$130 million) and SQM's PV park (US$111 million). The only rejection was the operational continuity of the Cobre Norte mine in Atacama.
View the data as a table
| Antofagasta | US$1,703.0 · 4 projects, including Tovaku |
| Atacama | US$232.7 · 3 approved and 1 rejected |
| Metropolitana | US$231.3 · 7 projects |
| Maule | US$204.0 · 3 projects |
| Coquimbo | US$45.0 · 1 project |
| Biobío | US$30.7 · 1 project |
| Los Lagos | US$19.1 · 3 projects |
| La Araucanía | US$12.1 · 1 project |
| O'Higgins | US$0.5 · 1 project |
| Region | Projects approved | Investment approved |
|---|---|---|
| Antofagasta | 4 | US$1,703 million |
| Atacama | 3 | US$232.7 million |
| Metropolitana | 7 | US$231.3 million |
| Maule | 3 | US$204 million |
| Interregional | 2 | US$143.6 million |
| Coquimbo | 1 | US$45 million |
| Biobío | 1 | US$30.7 million |
| Los Lagos | 3 | US$19.1 million |
| La Araucanía | 1 | US$12.1 million |
| O'Higgins | 1 | US$0.5 million |
Source: SEA, 4 November 2026. This year's series of energy investment approved by the SEA is in our story on the 90 projects worth US$11,855 million.
Does your company do environmental impact studies, baselines or SEIA consulting? Reach Energía Futura's readers.
See advertising formatsFrequently asked questions
How long does an environmental review take in Chile?
In 2025, on average, 399 days for a DIA and 1,124 days for an EIA, counted from filing to ruling and including suspensions.
What is the difference between a DIA and an EIA?
A DIA is for projects that declare no significant impacts; an EIA is mandatory when they do, for example on communities, glaciers or protected areas, and requires more studies and public participation.
Does the plan change environmental law?
No. It is an internal management plan: processes, workload, training and artificial intelligence. Legal changes to the SEIA follow a separate track.
How long does the 30% target run?
The plan covers 2026-2030 and applies to EIAs and DIAs filed during the current administration.