LATESTKerosene in Chile rises CLP 54 a litre from Thursday 26 and is up CLP 360 since October, while gasoline and diesel stay frozenChile's grid reform bill to reach Congress in early 2027Chile curtails 200 GWh of solar and wind power in one week as the grid operator plans a tender to reinforce the northCNE declares Zaldívar pipeline under construction
ENERGÍA FUTURA
Solar Energy

Chile curtails 200 GWh of solar and wind power in one week as the grid operator plans a tender to reinforce the north

By ·

Chile curtails 200 GWh of solar and wind power in one week as the grid operator plans a tender to reinforce the north

Curtailment of renewable energy remains the biggest problem in Chile's power system. In the week of 16 to 22 November, 200.64 GWh of solar and wind energy was cut, more than half of it on Saturday and Sunday, according to the weekly balance by Aclai Consultores using data from the Coordinador Eléctrico Nacional published on Wednesday. This is energy the plants could have produced but the system could neither use nor transport.

At the same time, the grid operator published its 2027 Ancillary Services Report, which sets a new tender to strengthen the northern grid. The requirement is to add at the Kimal substation, in Antofagasta, the equivalent of a 103 MVAr synchronous condenser, so that the Kimal-Lo Aguirre direct-current line can operate securely without forcing gas plants to run.

A week of wasted solar and wind powerWeek of 16-22 November 2026
200.64 GWhSolar and wind energy curtailedOver half at the weekend
US$15.5/MWhAverage marginal cost in the north
69.7%Time at US$5 or less in the north
View the data as a table
Solar and wind energy curtailed200.64 GWh
Average marginal cost in the northUS$15.5/MWh
Time at US$5 or less in the north69.7%

How much energy was lost to curtailment

According to ACERA's October bulletin, based on grid-operator data, 4,380 GWh of solar and wind energy was curtailed between January and October 2026, just 1.4% less than in the same period of 2025. October alone accounted for about 834 GWh, the difference between the total to October and the 3,546 GWh recorded to September.

It has been a wet year. In October, conventional hydropower supplied 35.6% of the system's electricity, solar 24.5% and wind 16.5%, while coal fell to 4.6%, 68.7% less than in October 2025, according to the same bulletin. With so much cheap energy, the system has more supply than it can consume or move during sunny hours. In 2025 curtailment had reached 6,205 GWh, as we reported in Deloitte's study on transmission.

IndicatorValuePeriod
Solar and wind energy curtailed200.64 GWh16-22 November 2026
Energy curtailed in the year4,380 GWhJanuary-October 2026
Change versus 2025−1.4%January-October
Conventional hydro generation35.6%October 2026
Coal generation4.6% (−68.7% year on year)October 2026

Source: Aclai Consultores using grid-operator data, via Electrominería; ACERA bulletin for October 2026.

Curtailment and zero marginal costs, even at night

Curtailment shows up in the marginal cost, the price at which energy is valued at each moment. In the week analysed, the average was US$15.5 per MWh in the north (Tarapacá to Nueva Pan de Azúcar), US$14.5 in the centre (Quillota to Ancoa) and US$12.5 at Charrúa. In the north the cost was at US$5 or less 69.7% of the time, in the centre 62.1% and at Charrúa 72.9%.

What is new is what happens at night. Between 23:00 and 07:59, the share of hours with a marginal cost of US$5 or less north of Charrúa went from 1% in November 2025 to 49% in November 2026, and south of Charrúa from 2% to 56%. During sunny hours it was already almost constant: 100% in the north. The shift coincides with a wet year and with more batteries charging at midday and discharging later. In May the marginal cost had already touched US$3.4 per MWh, its lowest since 2002.

Marginal costs now hit zero at night tooHours with marginal cost of US$5/MWh or less, 23:00-07:59, in November, north and south of Charrúa
View the data as a table
North, 20251%
North, 202649%
South, 20252%
South, 202656%
Hours at US$5 or less, by time block
Night (23:00-07:59)1%49%2%56%
Daylight (08:00-17:59)96%100%66%72%
Peak (18:00-22:59)20%37%18%35%

The south saw the opposite. On Monday 16 at 14:30, the marginal cost reached US$397.7 per MWh in Chiloé, US$377.9 in Puerto Montt and US$360.0 in Ciruelos, while Lastarria and Charrúa were at US$0. South of Lastarria there was price decoupling and congestion on Monday, Tuesday, Thursday and Friday, which the balance attributes to two 220 kV lines out of service since 17 October: Ciruelos-Cerros de Huichahue 2 and Cerros de Huichahue-Nueva Pichirropulli 2.

The south paid up to US$398/MWh while the centre was at zeroMarginal cost by node on Monday 16 November at 14:30, US$/MWh
View the data as a table
ChiloéUS$397.7
Puerto MonttUS$377.9
CiruelosUS$360.0
LastarriaUS$0.0
CharrúaUS$0.0
Synchronous condenser installed at an electrical substation
A synchronous condenser at a substation in Australia. These rotating machines produce no energy but give the grid strength. Photo: Mriya / Wikimedia Commons (CC BY-SA 3.0).

The tender to reinforce the Kimal substation

The other side of curtailment is stability. When most energy comes from solar, wind and battery plants connected through inverters, the grid loses the short-circuit power that the large rotating machines of thermal plants used to provide. Without that strength, a direct-current line such as Kimal-Lo Aguirre cannot operate securely.

The grid operator's report calculates that the Kimal 220 kV node needs an additional 606 MVA of short-circuit power. That is equivalent to a 103 MVAr synchronous condenser or a grid-forming (GFM) battery system of about 466 MVA, or any other technology with an equivalent contribution. The cost comparison is clear: covering the shortfall by running 124 MW of LNG-fired plants would cost about US$31.7 million a year, while the annualised investment for the upgrade would be US$3.4 million.

What the grid operator wants for the Kimal substation
103 MVArEquivalent synchronous condenserOr a grid-forming BESS of ~466 MVA
606 MVAAdditional short-circuit power
US$31.7 M/yrCost of covering it with forced LNG124 MW of gas dispatched
US$3.4 M/yrAnnualised cost of the upgrade
View the data as a table
Equivalent synchronous condenser103 MVAr
Additional short-circuit power606 MVA
Cost of covering it with forced LNGUS$31.7 M/yr
Annualised cost of the upgradeUS$3.4 M/yr

The report is open for comments until 7 December. Drafting of the tender rules will start in January and the preliminary tender launch is in July, the grid operator said. It noted that the measure reduces the need to keep conventional plants running only for security, lowers operating costs and makes it easier to use renewables. The Kimal-Lo Aguirre line itself is more than 22% built.

What the first northern tender delivered

This is not the first time. In May 2024 a voltage-control tender for the north concluded. Four new condensers were awarded, two to Consorcio Alupar (Ana María and Illapa) and two to Transelec (Ana María and Likanantai), plus the conversion of units at Engie's Tocopilla plant. The grid operator's press release says those facilities will start operating in the first months of 2027; the technical report sets their start from the second half of 2027.

What the first northern tender awarded (2024)
Consorcio AluparNew condenserAna María 220 kV1,851.0
Consorcio AluparNew condenserIllapa 220 kV1,493.0
Engie Energía ChileUnit conversionCentral Tocopilla 220 kV355.7
TranselecNew condenserAna María 220 kV1,993.4
TranselecNew condenserLikanantai 220 kV1,993.4
CompanyProjectNodeShort-circuit power
Consorcio AluparNew condenserAna María 220 kV1,851.0 MVA
Consorcio AluparNew condenserIllapa 220 kV1,493.0 MVA
Engie Energía ChileUnit conversionTocopilla plant 220 kV355.7 MVA
TranselecNew condenserAna María 220 kV1,993.4 MVA
TranselecNew condenserLikanantai 220 kV1,993.4 MVA

Source: Coordinador Eléctrico Nacional, 2027 Ancillary Services Report (table 6-1).

The new tender to strengthen the northern grid
  1. May 2024First northern tender concludes
  2. 23 November 20262027 ancillary services report published
  3. 7 December 2026Comment deadline
  4. January 2027Drafting of tender rules begins
  5. 20272024 condensers start operating
  6. July 2027Preliminary tender launch
Two direct-current transmission lines with steel towers crossing on a prairie
Direct-current lines in the United States. Kimal-Lo Aguirre will be Chile's first line of this kind and needs a strong grid at both ends. Photo: Zonk43 / Wikimedia Commons (CC BY-SA 3.0).

Does your company develop batteries, condensers or grid-stability solutions? Reach Energía Futura's readers.

See advertising formats

Frequently asked questions

What is energy curtailment?

It is solar or wind energy that plants could generate but that is cut because there is not enough demand or the grid cannot carry it.

How much energy was curtailed in 2026?

4,380 GWh between January and October, according to ACERA using grid-operator data, and 200.64 GWh in the week of 16-22 November alone.

What is a synchronous condenser?

It is a rotating machine connected to the grid that produces no energy but provides short-circuit power, inertia and voltage control, attributes that systems with lots of solar and wind lose.

When is the Kimal tender?

The rules will be drafted from January and the preliminary launch is July 2027. Comments on the report close on 7 December 2026.