LATESTSix data centers totaling 1,420 MW left on a waiting list in Chile due to lack of transmission capacityChile's Chamber of Deputies asks to expand Casa Solar, the program that co-finances home solar panelsAtlas Renewable Energy files a US$160 million Kimal line and battery plan for Alfa Solar in ChileVicente mini hydro plant would generate 3 MW from the Las Mercedes irrigation canal in Curacaví, Chile
ENERGÍA FUTURA
Sustainability & ESG

Chile's Kimal-Lo Aguirre HVDC line passes 22% construction progress and plans up to 7,000 workers

By ·

Chile's Kimal-Lo Aguirre HVDC line passes 22% construction progress and plans up to 7,000 workers

The Kimal-Lo Aguirre line, Chile's first high-voltage direct current (HVDC) line, passed 22% construction progress at the end of October 2026, according to the update from its developer, Conexión, reported by REDIMIN on November 4. About 1,500 people work on it today, and the company plans to reach about 7,000 as it opens new work fronts.

The 7,000-worker figure is not a contracted workforce and has no date: it depends on new sectoral authorizations, such as forestry permits, easements and land availability. The 1,346 km line, with up to 3,000 MW, will link the Kimal substation in María Elena (Antofagasta) with Lo Aguirre in Pudahuel (Metropolitan Region), with an investment of about US$1.5 billion.

Kimal-Lo Aguirre in figures
+22%Construction progressEnd of October 2026
1,346 kmLength
3,000 MWCapacity
1,500Workers todayProjects about 7,000
Source: Conexión, via REDIMIN
View the data as a table
Construction progress+22%
Length1,346 km
Capacity3,000 MW
Workers today1,500

Kimal-Lo Aguirre progress, report by report

Kimal-Lo Aguirre progress is tracked by Chile's grid operator, the Coordinador Eléctrico Nacional, in bimonthly reports. In May-June 2026 it recorded 19.7% actual construction progress, above the 17.6% planned. In August, the Coordinador reported 21.4% against 19.5% planned, according to REDIMIN. In September, Reporte Minero reported 20% of works done and US$422 million spent.

Construction is ahead of scheduleConstruction progress, % (Coordinador reports)
ActualPlanned
17%18%19%20%21%22%May-Jun 2026Aug 2026ActualPlanned
Source: Coordinador Eléctrico Nacional, via REDIMIN
View the data as a table
ActualPlanned
May-Jun 202619.7%17.6%
Aug 202621.4%19.5%
Cut-offActual construction progressPlanned progressSource
May-June 202619.7%17.6%Coordinador Eléctrico Nacional
August 202621.4%19.5%Coordinador, via REDIMIN
September 202620%—Reporte Minero
End of October 2026Over 22%—Conexión, via REDIMIN

The figures are not fully comparable: some measure construction only and others are rounded. Overall project progress, which adds engineering, permits and land management, was 57% in August against 54.31% planned, according to the Coordinador report cited by REDIMIN. That month, construction of the line and of the Lo Aguirre converter station were behind their own schedules, although the project as a whole was ahead.

Tower of a high-voltage direct current transmission line with its conductors
A tower of a high-voltage direct current (HVDC) line in Alberta, Canada. Kimal-Lo Aguirre will use that technology to move 3,000 MW over 1,346 km. Photo: TagaSanPedroAko / Wikimedia Commons (CC0).

What the Kimal-Lo Aguirre line is

The line will carry solar and wind power from the north to central Chile, where most demand is. It uses direct current because it loses less energy over long distances than alternating current. It will operate at ±600 kV in a bipolar scheme and cross 28 communes in 5 regions: Antofagasta, Atacama, Coquimbo, Valparaíso and the Metropolitan Region. At each end it will have converter stations, which turn alternating current into direct current and back.

The two ends of the Kimal-Lo Aguirre line1,346 km of direct current, 28 communes in 5 regions
KimalMaría Elena
Lo AguirrePudahuel
Source: Conexión and Coordinador Eléctrico Nacional (location by commune, approximate)
View the data as a table
KimalMaría Elena
Lo AguirrePudahuel

It was awarded in December 2021 to the consortium of Transelec, ISA Inversiones Chile and China Southern Power Grid International, with a bid annual remuneration of US$116.3 million. It will be one of the longest HVDC lines in the Americas, though far from China's records, as we show in the longest transmission line in the world.

FeatureValue
Length1,346 km
CapacityUp to 3,000 MW
Voltage±600 kV direct current
Route28 communes in 5 regions
InvestmentAbout US$1.5 billion
Spent by September 2026US$422 million
Structures with works underwayAbout 200
Current workersAbout 1,500
Projected workersAbout 7,000 (subject to permits)
Planned commercial operation2029

Sources: Conexión and Coordinador Eléctrico Nacional, via REDIMIN (November 4, 2026) and Reporte Minero (September 10). Other sources give slightly different lengths depending on how the route is measured.

With US$422 million spent by September out of a total of about US$1.5 billion, the project has used about 28% of its budget, a share consistent with physical progress of just over a fifth: in works of this kind, equipment such as conductors, insulators and converter station transformers is paid for before it shows on the ground. In the Antofagasta Region, according to information published in August, the route covers 415.2 km and 829 towers, almost a third of the line. The rest runs south through Atacama, Coquimbo and Valparaíso to the Metropolitan Region, where the Lo Aguirre converter station will receive the power and feed it into the alternating current grid.

Does your company work in power transmission or renewables? Reach Energía Futura's readers.

See advertising options

Permits, the bottleneck

The line received its favorable environmental approval in November 2025, and construction formally began in February 2026. But environmental approval is not enough: the route requires about 5,000 sectoral and environmental permits across the five regions, which the company and the Coordinador track one by one. That is why staffing depends on forestry permits, easements and land release.

Kimal-Lo Aguirre milestones
  1. December 2021Awarded to Transelec, ISA and China Southern Power Grid
  2. November 2025Favorable environmental approval
  3. February 2026Construction formally starts
  4. August 202621.4% construction progress
  5. October 2026Passes 22% with 1,500 workers
  6. 2029Planned commercial operation
Source: Coordinador Eléctrico Nacional, Conexión, REDIMIN, Reporte Minero and Bloomberg Línea

Conexión's sustainability and public affairs manager, Carola Venegas, presented the update at the Future Energy Summit, held in Santiago on October 28-29. Works are now concentrated in María Elena and Pudahuel, with about 200 structures in progress. The next steps are opening new fronts, assembling structures and building the converter stations. Financing is closed with international banks, and disbursements depend on meeting environmental, social and governance requirements.

Why Kimal-Lo Aguirre matters for curtailment

Chile loses renewable energy every year that it cannot transport. Deloitte estimated 2025 curtailment at 6,205 GWh, as we reported in our story on a grid that cannot carry the available energy. With 3,000 MW of capacity, Kimal-Lo Aguirre is the project that can do the most to reduce that waste after 2029.

It is not the only one. Investment in power transmission in Chile grew ninefold in 2026, to US$3,276 million in 48 works, as we detailed in our story on transmission investment. And the government is preparing a portfolio of 20 strategic energy projects, mainly lines and storage, to shorten their permitting before 2030.

High-voltage lines crossing a landscape in Chile
High-voltage lines in Chile. Today's alternating current grid cannot carry all the northern solar power to the center of the country. Photo: ShootingStarMax / Wikimedia Commons (CC BY-SA 4.0).

Frequently asked questions

How far along is Kimal-Lo Aguirre construction?

Over 22% at the end of October 2026, according to the company. The Coordinador had reported 21.4% in August.

How many workers does it have?

About 1,500. The company plans to reach about 7,000, subject to new permits and with no set date.

When will it start operating?

Commercial operation is planned for 2029.

Who is building it?

Conexión, the company of Transelec, ISA Inversiones Chile and China Southern Power Grid International, which won the tender in 2021.

Why does it use direct current?

Because over long distances it loses less energy than alternating current and allows precise control of how much power is carried.