The Independent Energy Generators Association (GIE) has filed a complaint with the Superintendency of Electricity and Fuels (SEC) against Chile's National Electricity Coordinator over the order capping the output of a group of small distributed generation plants (PMGD) at 15% of their installed capacity. The restriction has applied since 10 November and, fourteen days later, still has no end date.
The association does not dispute that the Coordinador can act preventively in the face of a risk to the system. What it complains about, according to the text quoted by Revista Electricidad on Monday, is a possible mismatch between that risk and the size, scope and duration of the restriction. It asks the SEC to open an investigation and to require the Coordinador to produce the studies behind the cap.
View the data as a table
| Maximum injection allowed | 15% |
| PMGD output lost on 8 Nov | 520 MW |
| Output of a 9 MW plant under the cap | 1.35 MW |
| Days the cap has been in force | 14 |
Why the Coordinador capped the PMGD plants
The measure is the response to the fault on Sunday 8 November at 14:54. A fault on 220 kV facilities between the Chena and Cerro Navia substations in Santiago was cleared in about 75 milliseconds, but at that instant 520 MW of PMGD tripped off in the Santiago Metropolitan, Valparaíso and O'Higgins regions. Frequency dropped to 48.93 Hz, as we explained in our story on the 15% cap on PMGD.
The next day, the Coordinador requested technical records and ordered the preventive injection limit equivalent to 15% for the listed plants, citing the need to protect the security of the National Electricity System while it checks how their protections and controls behaved. PMGD are plants of up to 9 MW connected to distribution grids; under the cap, a 9 MW plant cannot deliver more than 1.35 MW, even when the sun would let it produce much more.
- 8 Nov, 14:54220 kV faultBetween Chena and Cerro Navia; 520 MW of PMGD trip off.
- 9 NovCoordinador's instructionPreventive 15% cap on the listed PMGD (art. 102 of DS 88).
- 10 NovCap takes effect
- 12 NovGrenergy asks to lift it for eight plants
- 17 NovSecurity report GO 25/2026261 PMGD critical to the system (1,280 MW).
- 23 NovGIE files a complaint against the Coordinador with the SECAsks for an investigation and a prompt reassessment.
- 19 Aug 2027Deadline for the new anti-islanding settingsExtended by CNE Exempt Res. 412/2026.

What GIE is reporting to the SEC
The filing cites a possible breach of article 102 of Supreme Decree No. 88 of 2019, the regulation on small generation plants, which is the same rule the Coordinador used to impose the measure. There are three objections: how the percentage was justified, on what basis the plants were selected and why the restriction has no time limit.
On the last point, the complaint says the instruction sets no review milestones or verifiable parameters to decide whether it continues, nor specific actions companies could take to reverse or mitigate its effects. In practice, plant owners do not know what they must prove to have the cap lifted.
| Open an investigation | For a possible breach of article 102 of DS 88 of 2019 |
| Request the Coordinador's records | Risk studies, the 15% calculation, selection criteria and operating records |
| Reassess the measure | Promptly, to modify it or lift it fully or partly |
| Review the pro rata rule | Whether it should apply to the capacity in the Connection Criteria Reports (ICC) |
| Assess penalties | Corrective measures if regulatory breaches are proven |
GIE also asks that, if the measure stays in force, the SEC order a prompt reassessment to modify or lift it, fully or partly, if system security allows, and that it consider corrective measures or penalties if breaches are proven. Source: Revista Electricidad, 23 November 2026.
The cost of the 15% cap for PMGD plants
The economic argument is direct: according to the complaint, every period in which available output exceeds the cap means energy not injected and revenue lost. In November, with long clear days in central Chile, a solar plant runs close to its maximum for several hours a day, so in those hours the cut can reach 85% of what it would produce.
The association asks for a review of whether the measure meets the rules' economic efficiency criteria and pro rata rules. In particular, it argues the limit could have been calculated on the injection capacity set in each plant's Connection Criteria Reports (ICC), which may differ from the installed capacity the Coordinador used as the base.
| PMGD capacity | Maximum output under the cap | Capacity it cannot inject |
|---|---|---|
| 3 MW | 0.45 MW | 2.55 MW |
| 6 MW | 0.9 MW | 5.1 MW |
| 9 MW | 1.35 MW | 7.65 MW |
Energía Futura calculation using 15% of installed capacity. The real loss depends on how much each plant produces each hour; neither the Coordinador nor GIE has published the total energy curtailed since 10 November.

Anti-islanding protection at the heart of the debate
GIE gathered records from its members and concluded that, at most of their plants, the 8 November disconnection was due to the vector-shift anti-islanding function. It is a protection that detects sudden changes in the voltage angle and disconnects the plant so it does not keep energising an isolated stretch of grid. Spain's Grenergy gave the same explanation when it asked for the cap to be lifted at eight of its plants.
The legal point is the deadline. Exempt Resolution No. 412 of 2026 from the National Energy Commission (CNE) extended until 19 August 2027 the deadline to implement the new settings for that protection required by the PMGD technical standard. Since that deadline was still running on the day of the fault, GIE argues that plants cannot be blamed for failing an obligation that has not yet fallen due, although it accepts that this transitional regime does not prevent properly justified security measures.
The case overlaps with the wider debate on the weight of PMGD in the system. On 17 November, the Coordinador itself identified 261 PMGD with 1,280 MW whose withdrawal would put supply at risk, as we detailed in our story on the security report on small plants. In other words, the system needs these plants and, at the same time, requires them to ride through distant faults without tripping.
The SEC has not said whether it will open an investigation.
Does your company develop, operate or protect PMGD solar plants? Reach Energía Futura's readers.
See advertising formatsFrequently asked questions
What is a PMGD?
A small distributed generation plant: a power plant of up to 9 MW connected to a distributor's grid. Most are solar plants.
What is GIE?
The Independent Energy Generators Association, which groups independent power producers, several of which own PMGD plants.
How long will the 15% cap last?
It has no end date. It has applied since 10 November 2026 and will stay until the Coordinador changes or lifts it.
What can the SEC do?
It can open an investigation, request records from the Coordinador and start penalty proceedings if it finds regulatory breaches.