LATESTChile's 2026 tailings registerSQM earns US$1.569 billion through September, up 288% on lithium, but expects lower pricesMetro and Transelec prepare the Cerro Navia substation that will power Santiago's Lines 7, 9 and AEcoVera Territorium proposes a US$800 million plant to turn Santiago's waste into 800 GWh of electricity
ENERGÍA FUTURA
Wind Energy

Enel's Cerro Los Loros wind farm in Ovalle, Chile, is approved: 64 MW and US$150 million

By ·

Enel's Cerro Los Loros wind farm in Ovalle, Chile, is approved: 64 MW and US$150 million

The Coquimbo Environmental Evaluation Commission has approved, with conditions, the environmental impact study for the Cerro Los Loros wind farm of Enel Green Power Chile, to be built on the coast of Ovalle. The project will have 8 turbines of 8 MW, for 64 MW of capacity, and an investment of US$150 million, Revista Electricidad reported on Tuesday 17 November.

The farm will be located near the town of Los Loros and the El Toro cove, will cover 53.4 hectares and have a service life of 37 years. Its power will run through a 36.8-kilometre underground line to the substation of Enel's Talinay Oriente plant, and from there to the National Electric System. Construction could employ up to 500 people.

Cerro Los Loros wind farm
64 MWCapacity8 turbines of 8 MW
US$150 millionInvestmentEnel Green Power Chile
36.8 kmUnderground lineTo the Talinay Oriente substation
Up to 500Construction jobs37-year service life
Source: Revista Electricidad, 17 Nov 2026
View the data as a table
Capacity64 MW
InvestmentUS$150 million
Underground line36.8 km
Construction jobsUp to 500

What the Cerro Los Loros wind farm will look like

With 8 MW per machine, the farm reaches with eight turbines a capacity that used to require many more units. The trend towards larger machines is global, as our ranking of the world's largest wind turbine shows.

FeatureCerro Los Loros wind farm
OwnerEnel Green Power Chile
LocationCoast of Ovalle, near Los Loros and El Toro cove (Coquimbo Region)
Turbines8 of 8 MW
Total capacity64 MW
InvestmentUS$150 million
Area53.4 hectares
Connection36.8 km underground line to the Talinay Oriente substation
Service life37 years
JobsUp to 500 people during construction

Source: Coquimbo Region Environmental Evaluation Commission, via Revista Electricidad, 17 November 2026.

El Toro cove at night, on the coast of Ovalle
El Toro cove, on the coast of Ovalle, next to which the farm will be built. The environmental agency held a public participation activity there in February 2025. Photo: Thasebas / Wikimedia Commons (CC BY-SA 4.0).

A smaller project than the original

When Enel submitted the study to the Environmental Impact Assessment System on 9 January 2025, the farm had 11 turbines of 7.2 MW, up to 79 MW, and a 30 MW / 120 MWh battery system, with about 570 workers during construction, according to REDIMIN. During the review, the agency asked for clarifications in two rounds, the company suspended deadlines and the design changed: one of the documents in the file mentions relocating one turbine and removing three units on the Los Loros hill.

FeatureEIA filed (January 2025)Approved project (November 2026)
Turbines11 of 7.2 MW8 of 8 MW
CapacityUp to 79 MW64 MW
Batteries30 MW / 120 MWhNot mentioned in the approval
InvestmentUS$150 millionUS$150 million
Construction jobsAbout 570 workersUp to 500 people

Source: REDIMIN (17 January 2025), with EIA data, and Revista Electricidad (17 November 2026).

The project shrank during its reviewWind farm capacity, MW
Source: REDIMIN, 17 Jan 2025 (original EIA), and Revista Electricidad, 17 Nov 2026 (approved project)
View the data as a table
2025 EIA79.2 MW · 11 turbines of 7.2 MW
Approved 202664.0 MW · 8 turbines of 8 MW
Battery (2025 EIA)30.0 MW · 30 MW / 120 MWh; the approval note does not mention it

The approved version keeps the US$150 million investment but uses 8 larger machines and 15 MW less capacity. Regional authorities did not mention the battery when announcing the approval, so it is unclear whether it remains in the project. The project shares works with the Talinay wind farm, which has had its environmental permit since 2009, and some of its access roads connect with those of Talinay II.

Cerro Los Loros' environmental review
  1. 9 Jan 2025EIA filed11 turbines, up to 79 MW and a 30 MW battery.
  2. 19 Feb 2025Public participationSEA activity in Caleta El Toro.
  3. 2025-2026Clarifications and redesignIcsara requests and deadline suspensions; the farm drops to 8 turbines of 8 MW.
  4. 17 Nov 2026Approved with conditionsCoquimbo's Evaluation Commission approves the EIA.
Source: REDIMIN, 17 Jan 2025 (original EIA), and Revista Electricidad, 17 Nov 2026 (approved project)

Does your company build, operate or supply wind farms? Reach Energía Futura's readers.

See advertising options

What Coquimbo officials said about the wind farm

The regional presidential delegate, Víctor Pino, said the region is giving *«signs of economic reactivation for the region, for the arrival of foreign investment»*. The regional energy secretary, Cristhian Acori, said the project *«will add renewable energy to our energy mix»*, and the regional environment secretary, Jovanka Rendic, said the review *«rigorously considered the environmental components and the safeguards established»*.

Like any environmental permit, the approval can still be challenged before the Committee of Ministers or the environmental courts. The company has not announced a construction start date.

What comes next for the Cerro Los Loros wind farm

With the environmental permit in hand, Enel must obtain the sectoral permits issued by other agencies and meet the conditions set by the Evaluation Commission, which have not yet been published in detail. The connection to the Talinay Oriente substation, which the company already owns, removes one of the usual bottlenecks for new farms: securing grid capacity.

The project joins a wind pipeline that is growing more slowly than solar. According to the September 2026 bulletin from Generadoras de Chile, based on CNE data, there were 346 MW of wind under construction in 12 projects, compared with 3,023 MW of solar. Under environmental review, however, wind adds up to 1,934 MW in 10 projects, with an investment of US$3,754 million, plus two hybrid solar and wind projects totalling 1,695 MW.

Generation in Chile, excluding batteriesWindSolar PV
Under construction346 MW (12 projects)3,023 MW (144 projects)
Under environmental review1,934 MW (10 projects)3,985 MW (34 projects)
Investment under reviewUS$3,754 millionUS$5,262 million

Source: Generadoras de Chile, September 2026 bulletin, based on CNE data. Cerro Los Loros now moves from the «under review» column to the approved projects.

Turbines of the El Arrayán wind farm on the coast of Ovalle
The El Arrayán wind farm, on the coastal slopes of the Altos de Talinay, in the same municipality of Ovalle. Photo: Alfabille / Wikimedia Commons (CC BY-SA 4.0).

Coquimbo, one of Chile's windiest regions

The coast of the Coquimbo Region, between Ovalle and Canela, is home to several of Chile's first wind farms: Canela, Talinay, El Arrayán, Punta Palmeras and Los Cururos, among others. Worldwide, today's largest farms are measured in thousands of megawatts, as our ranking of the world's largest wind farm shows.

Nationally, wind generated 13.1% of Chile's electricity in 2025, according to Ember, as shown in our ranking of countries where wind power weighs most. Projects such as Cerro Los Loros add capacity in a region with good grid access, although 64 MW is a fraction of the 200 MW-plus farms now under review in the south.

Frequently asked questions

Where will the Cerro Los Loros wind farm be?

On the coast of the municipality of Ovalle, Coquimbo Region, near the town of Los Loros and El Toro cove.

How many MW will it have?

64 MW, with 8 turbines of 8 MW each.

How much does the project cost?

The estimated investment is US$150 million.

Who owns it?

Enel Green Power Chile, which also operates the Talinay farm in the same area.