The Coquimbo Environmental Evaluation Commission has approved, with conditions, the environmental impact study for the Cerro Los Loros wind farm of Enel Green Power Chile, to be built on the coast of Ovalle. The project will have 8 turbines of 8 MW, for 64 MW of capacity, and an investment of US$150 million, Revista Electricidad reported on Tuesday 17 November.
The farm will be located near the town of Los Loros and the El Toro cove, will cover 53.4 hectares and have a service life of 37 years. Its power will run through a 36.8-kilometre underground line to the substation of Enel's Talinay Oriente plant, and from there to the National Electric System. Construction could employ up to 500 people.
View the data as a table
| Capacity | 64 MW |
| Investment | US$150 million |
| Underground line | 36.8 km |
| Construction jobs | Up to 500 |
What the Cerro Los Loros wind farm will look like
With 8 MW per machine, the farm reaches with eight turbines a capacity that used to require many more units. The trend towards larger machines is global, as our ranking of the world's largest wind turbine shows.
| Feature | Cerro Los Loros wind farm |
|---|---|
| Owner | Enel Green Power Chile |
| Location | Coast of Ovalle, near Los Loros and El Toro cove (Coquimbo Region) |
| Turbines | 8 of 8 MW |
| Total capacity | 64 MW |
| Investment | US$150 million |
| Area | 53.4 hectares |
| Connection | 36.8 km underground line to the Talinay Oriente substation |
| Service life | 37 years |
| Jobs | Up to 500 people during construction |
Source: Coquimbo Region Environmental Evaluation Commission, via Revista Electricidad, 17 November 2026.

A smaller project than the original
When Enel submitted the study to the Environmental Impact Assessment System on 9 January 2025, the farm had 11 turbines of 7.2 MW, up to 79 MW, and a 30 MW / 120 MWh battery system, with about 570 workers during construction, according to REDIMIN. During the review, the agency asked for clarifications in two rounds, the company suspended deadlines and the design changed: one of the documents in the file mentions relocating one turbine and removing three units on the Los Loros hill.
| Feature | EIA filed (January 2025) | Approved project (November 2026) |
|---|---|---|
| Turbines | 11 of 7.2 MW | 8 of 8 MW |
| Capacity | Up to 79 MW | 64 MW |
| Batteries | 30 MW / 120 MWh | Not mentioned in the approval |
| Investment | US$150 million | US$150 million |
| Construction jobs | About 570 workers | Up to 500 people |
Source: REDIMIN (17 January 2025), with EIA data, and Revista Electricidad (17 November 2026).
The approved version keeps the US$150 million investment but uses 8 larger machines and 15 MW less capacity. Regional authorities did not mention the battery when announcing the approval, so it is unclear whether it remains in the project. The project shares works with the Talinay wind farm, which has had its environmental permit since 2009, and some of its access roads connect with those of Talinay II.
- 9 Jan 2025EIA filed11 turbines, up to 79 MW and a 30 MW battery.
- 19 Feb 2025Public participationSEA activity in Caleta El Toro.
- 2025-2026Clarifications and redesignIcsara requests and deadline suspensions; the farm drops to 8 turbines of 8 MW.
- 17 Nov 2026Approved with conditionsCoquimbo's Evaluation Commission approves the EIA.
Does your company build, operate or supply wind farms? Reach Energía Futura's readers.
See advertising optionsWhat Coquimbo officials said about the wind farm
The regional presidential delegate, Víctor Pino, said the region is giving *«signs of economic reactivation for the region, for the arrival of foreign investment»*. The regional energy secretary, Cristhian Acori, said the project *«will add renewable energy to our energy mix»*, and the regional environment secretary, Jovanka Rendic, said the review *«rigorously considered the environmental components and the safeguards established»*.
Like any environmental permit, the approval can still be challenged before the Committee of Ministers or the environmental courts. The company has not announced a construction start date.
What comes next for the Cerro Los Loros wind farm
With the environmental permit in hand, Enel must obtain the sectoral permits issued by other agencies and meet the conditions set by the Evaluation Commission, which have not yet been published in detail. The connection to the Talinay Oriente substation, which the company already owns, removes one of the usual bottlenecks for new farms: securing grid capacity.
The project joins a wind pipeline that is growing more slowly than solar. According to the September 2026 bulletin from Generadoras de Chile, based on CNE data, there were 346 MW of wind under construction in 12 projects, compared with 3,023 MW of solar. Under environmental review, however, wind adds up to 1,934 MW in 10 projects, with an investment of US$3,754 million, plus two hybrid solar and wind projects totalling 1,695 MW.
| Generation in Chile, excluding batteries | Wind | Solar PV |
|---|---|---|
| Under construction | 346 MW (12 projects) | 3,023 MW (144 projects) |
| Under environmental review | 1,934 MW (10 projects) | 3,985 MW (34 projects) |
| Investment under review | US$3,754 million | US$5,262 million |
Source: Generadoras de Chile, September 2026 bulletin, based on CNE data. Cerro Los Loros now moves from the «under review» column to the approved projects.

Coquimbo, one of Chile's windiest regions
The coast of the Coquimbo Region, between Ovalle and Canela, is home to several of Chile's first wind farms: Canela, Talinay, El Arrayán, Punta Palmeras and Los Cururos, among others. Worldwide, today's largest farms are measured in thousands of megawatts, as our ranking of the world's largest wind farm shows.
Nationally, wind generated 13.1% of Chile's electricity in 2025, according to Ember, as shown in our ranking of countries where wind power weighs most. Projects such as Cerro Los Loros add capacity in a region with good grid access, although 64 MW is a fraction of the 200 MW-plus farms now under review in the south.
Frequently asked questions
Where will the Cerro Los Loros wind farm be?
On the coast of the municipality of Ovalle, Coquimbo Region, near the town of Los Loros and El Toro cove.
How many MW will it have?
64 MW, with 8 turbines of 8 MW each.
How much does the project cost?
The estimated investment is US$150 million.
Who owns it?
Enel Green Power Chile, which also operates the Talinay farm in the same area.