Escondida adds Auren: Sungrow files a second 35 MW solar plant with batteries for US$61 million

By ·

Escondida adds Auren: Sungrow files a second 35 MW solar plant with batteries for US$61 million

Minera Escondida is adding a second solar-plus-battery project within its operation. Sungrow Power Chile, through its company Parque Artemis II, filed an Environmental Impact Statement (DIA) with Chile's environmental assessment system (SEIA) for the Auren project: a 35 MWac photovoltaic plant and a 35 MW lithium-ion battery system, with an investment of US$61 million, Revista Electricidad reported on 26 November 2026.

The power will go mainly to the operations of Escondida, the world's largest copper mine, run by BHP in the Antofagasta region. Auren joins Helia, a 75 MW project Sungrow filed in October. Together they add up to 110 MW: exactly the solar capacity BHP announced in June in its agreement with Sungrow for Escondida.

Auren in four figures
35 MWacSolar capacityPlus 35 MW of lithium-ion batteries
US$61 millionInvestment
5.7 km13.8 kV lines to Sulfuros substation
21 years 5 monthsUseful lifeWorks from July 2028
View the data as a table
Solar capacity35 MWac
InvestmentUS$61 million
13.8 kV lines to Sulfuros substation5.7 km
Useful life21 years 5 months

What the Auren project is

Auren will be built in the district of Antofagasta, with panels on solar trackers that turn to follow the sun. Its batteries will store part of the output from the sunniest hours to deliver it when generation drops or the mine's demand rises. According to the filing, the aim is to support the security and resilience of Escondida's power supply.

Power will be exported through two 13.8 kV medium-voltage lines, 5.7 kilometres long, to Minera Escondida's Sulfuros substation. The project may also feed the National Electric System if required. Works would start in July 2028 and its useful life is 21 years and five months.

FeatureAuren
OwnerParque Artemis II (Sungrow Power Chile)
InvestmentUS$61 million
Solar capacity35 MWac
Batteries35 MW, lithium-ion (MWh not disclosed)
DistrictAntofagasta
Connection2 lines of 13.8 kV and 5.7 km to Escondida's Sulfuros substation
Power offtakerMainly Minera Escondida; may feed the national grid
Filing typeDIA
Planned start of worksJuly 2028
Useful life21 years and 5 months

Source: Revista Electricidad, 26 November 2026, based on the DIA. As with Helia, the filing states that the owner will manage and operate the plant independently of the power's customers and will be responsible for its environmental obligations.

View from space of the Escondida mine area and its tailings dam in the desert
Escondida seen from the International Space Station in 2009, with its tailings dam at the centre. Photo: Expedition 22 crew, NASA / Wikimedia Commons (public domain).

Helia, Auren and Cenit: Sungrow's solar for BHP

In June, BHP reported long-term agreements with Sungrow to build solar generation and batteries at its sites: 110 MW of solar and 110 MW / 540 MWh of storage at Escondida, and 85 MW of solar and 85 MW / 420 MWh at Spence, operating from fiscal year 2029, according to Reporte Minero.

The first two projects were filed in October: Helia, 75 MW and US$110 million, at Escondida, as we reported in the solar plant inside Escondida, and Cenit, 20 MW and 100.3 MWh, for US$40 million, at Spence. With Auren, the solar capacity filed for Escondida reaches the agreement's 110 MW. At Spence, by contrast, 65 MW have yet to be filed.

Helia and Auren add up to the 110 MW agreed for EscondidaSolar capacity agreed between BHP and Sungrow and projects already filed, MW
HeliaAurenCenitNot yet filed
Source: Reporte Minero, BHP-Sungrow agreement (1 June 2026) and each project's filing
View the data as a table
HeliaAurenCenitNot yet filed
Escondida75 MW35 MW0 MW0 MW
Spence0 MW0 MW20 MW65 MW
ProjectMineCompanySolarBatteriesInvestmentFiled
HeliaEscondidaParque Artemis I75 MWac75 MWUS$110 millionOctober 2026
AurenEscondidaParque Artemis II35 MWac35 MWUS$61 millionNovember 2026
CenitSpenceParque Apolo I20 MWac100.3 MWhUS$40 millionOctober 2026
Total130 MWUS$211 million

Source: SEIA and REDIMIN (Helia), Reporte Minero (Cenit) and Revista Electricidad (Auren). The investment total is Energía Futura's sum. BHP's agreement refers to 540 MWh of batteries at Escondida; the Helia and Auren filings published so far do not detail energy in MWh.

Sungrow's three projects for BHP's minesSolar capacity, MWac
View the data as a table
Helia (Escondida)75 MW · US$110 M
Auren (Escondida)35 MW · US$61 M
Cenit (Spence)20 MW · US$40 M · 100,3 MWh
Where Sungrow's solar plants for BHP will goReference location of each mine; value = solar MW
Spence: Cenit20 MW · 100,3 MWh
Escondida: Helia and Auren75 + 35 MW
View the data as a table
Escondida: Helia and Auren75 + 35 MW
Spence: Cenit20 MW · 100,3 MWh

Why Escondida produces its own solar power

Escondida and Spence have used 100% renewable electricity since fiscal year 2022, thanks to long-term contracts. On-site plants do not replace those contracts: they complement them with generation at the point of consumption. «By locating generation directly at the point of consumption, we strengthen the resilience and efficiency of our operations' energy supply», said Adam Favero, BHP's vice-president of Development and Strategic Services, in June.

BHP also argues that generating on site eases pressure and congestion on the grid. It is a well-known problem in the north: during sunny hours some solar power cannot travel for lack of transmission capacity. Batteries at the mine also provide backup against grid failures, such as the February 2025 blackout that halted large mining operations.

The miner has also launched a tender to contract up to 6 TWh a year of renewable electricity for Escondida and Spence, with contracts of up to 20 years and supply from 2032. Large-scale mining is one of the biggest buyers of clean energy in the country, as our analysis of how much renewable energy each major miner uses shows.

From agreement to project: BHP's on-site solar
  1. Fiscal year 2022Escondida and Spence reach 100% renewable power via contracts
  2. 1 June 2026BHP announces Sungrow deals: 110 MW at Escondida and 85 MW at Spence
  3. 27 October 2026Helia (75 MW) and Cenit (20 MW) are filed
  4. November 2026Auren (35 MW) is filed
  5. July 2028Planned start of works at Helia, Auren and Cenit
  6. Fiscal year 2029BHP expects the projects to be operating
Source: Reporte Minero, BHP-Sungrow agreement (1 June 2026) and each project's filing

The size of the operation explains the bet. Escondida produced 1,347,600 tonnes of copper in 2025 and remains the world's largest copper mine. BHP has said Escondida and Spence account for about 9% of Chile's electricity demand, so 110 MW of on-site capacity is a fraction of its consumption, but one that sits inside the mine and comes with backup batteries.

Rows of solar panels on trackers in the desert
Panels on solar trackers at a plant in the Antofagasta region. Auren will use this technology, which turns the modules to follow the sun. Photo: ESO / Wikimedia Commons (CC BY 4.0).
  • Status: DIA filed in November 2026, at the admission stage.
  • Missing figure: Auren's battery capacity in MWh.
  • Spence: 65 MW of solar under the Sungrow agreement are yet to be filed.
  • BHP's target: projects operating from fiscal year 2029.

Does your company provide energy, storage or services to mining? Reach Energía Futura's readers.

See advertising options

Frequently asked questions

What is the Auren project?

A 35 MWac solar plant with 35 MW of batteries that Sungrow plans to supply Minera Escondida, with an investment of US$61 million.

How is it different from Helia?

Helia is larger (75 MW and US$110 million) and connects to the Laguna Seca substation. Auren connects to the Sulfuros substation. Together they make up the 110 MW agreed between BHP and Sungrow for Escondida.

Wasn't Escondida already using renewable power?

Yes, 100% renewable since fiscal year 2022 through contracts. On-site plants add generation and backup inside the mine.

When would it start operating?

Works are planned from July 2028, and BHP expects the projects to be operating in fiscal year 2029.