LATESTSix data centers totaling 1,420 MW left on a waiting list in Chile due to lack of transmission capacityChile's Chamber of Deputies asks to expand Casa Solar, the program that co-finances home solar panelsAtlas Renewable Energy files a US$160 million Kimal line and battery plan for Alfa Solar in ChileVicente mini hydro plant would generate 3 MW from the Las Mercedes irrigation canal in Curacaví, Chile
ENERGÍA FUTURA
Sustainability & ESG

Six data centers totaling 1,420 MW left on a waiting list in Chile due to lack of transmission capacity

By ·

Six data centers totaling 1,420 MW left on a waiting list in Chile due to lack of transmission capacity

Having land, financing and customers is no longer enough to build a data center in central Chile. At least six connection requests from data centers, totaling 1,420 MW, received unfavorable responses from the National Electricity Coordinator (CEN) and were placed on a waiting list because the substations they wanted to connect to have no spare capacity, La Tercera reported on November 7, citing letters from the Coordinator and the industry group Transmisoras de Chile.

That figure is four times the power currently drawn by the roughly seven data centers in operation on the CEN's list, which together require about 350 MW and are concentrated in Quilicura. The 1,420 MW is requested capacity, not actual consumption, and none of the projects has announced a final cancellation.

The grid, the new limit for data centers
1,420 MWRequested capacity on the waiting list6 rejected requests
350 MWData centers in operationabout 7, mostly in Quilicura
30%Transmission works on scheduleaccording to Transmisoras de Chile
Source: National Electricity Coordinator via La Tercera and Redimin
View the data as a table
Requested capacity on the waiting list1,420 MW
Data centers in operation350 MW
Transmission works on schedule30%

The data centers that could not connect

The list published by La Tercera and Redimin shows two waves of rejections. In 2025, connections were denied in Buin-Maipo and Colina-Chicureo; in 2026, in Tiltil-Polpaico and Lampa. The largest project is DC SC2, at 500 MW, which developer RTB Energy asked to connect at the 500 kV Polpaico substation and which was put on hold "with no room for new connections".

ProjectMunicipality or areaRequested capacityYear rejected
DC SC2Tiltil-Polpaico500 MW2026
DC STMColina-Chicureo220 MW2025
DC Alto JahuelBuin-Maipo200 MW2025
DC IrisLampa-Nueva Lampa100 MW2026
Campus NorteColina-ChicureoNot disclosed2025
Campus Norte Stage IIColina-ChicureoNot disclosed2025
Total1,420 MW

Source: National Electricity Coordinator, via La Tercera and Redimin (November 7, 2026). Projects with disclosed capacity add up to 1,020 MW; the remaining 400 MW would correspond to the two Campus Norte stages, whose breakdown was not published.

Data centers with rejected connections, by requested capacity (MW)
Campus Norte and Campus Norte Stage II (Colina) have no breakdown; together they would account for about 400 MW.Source: National Electricity Coordinator via La Tercera and Redimin
View the data as a table
DC SC2 (Tiltil-Polpaico, 2026)500 MW
DC STM (Colina-Chicureo, 2025)220 MW
DC Alto Jahuel (Buin-Maipo, 2025)200 MW
DC Iris (Lampa, 2026)100 MW

Other cases are also in limbo. Santiago Chile 4, a 150 MW project in Quilicura, and Curauma Phase 2, in the Valparaíso Region, are waiting for transmission works that were postponed. Data Center Sur, a 120 MW project in Puente Alto, was authorized with an overload warning and possible consumption limits, and its request was later withdrawn without a stated reason.

Where the data centers waiting for a connection are
Rejected 2026Rejected 2025Awaiting worksRequest withdrawn
Curauma Fase 2
DC SC2500 MW
DC STM / Campus Norte220 MW
DC Iris100 MW
Santiago Chile 4150 MW
Data Center Sur120 MW
DC Alto Jahuel200 MW
Approximate location based on the municipality or area reported.Source: National Electricity Coordinator via La Tercera and Redimin
View the data as a table
DC SC2Rejected 2026500 MW
DC IrisRejected 2026100 MW
DC STM / Campus NorteRejected 2025220 MW
DC Alto JahuelRejected 2025200 MW
Santiago Chile 4Awaiting works150 MW
Curauma Fase 2Awaiting worksValparaíso
Data Center SurRequest withdrawn120 MW
High-voltage electrical substation with transformers, gantries and a control building
A high-voltage substation. Data centers must connect to a substation with available capacity, and several in northern Santiago no longer have it. Photo: Aciarium / Wikimedia Commons (CC BY-SA 4.0).

Why transmission is holding back data centers

The problem is timing. A data center can be planned and built in a few years, while a transmission project takes five to seven years to go through planning, tendering, permitting and construction. "Data centers have to connect to substations and they can't," summed up Javier Tapia, executive director of Transmisoras de Chile, in the interview with La Tercera.

According to the industry group, only about 30% of the transmission works in its assessment are progressing on schedule, due to permitting delays and disputes with landowners. Tapia also said the expansion plan "falls short" and that the price cap set by the National Energy Commission (CNE) for some tenders "is out of line with the market", leaving some processes without bidders.

A University of Chile study commissioned by the group estimated a couple of years ago that about US$2 billion is needed to bring the grid up to date, mainly in zonal transmission, which carries power from the backbone system to cities. For reference, the Coordinator has just awarded 17 transmission projects worth US$475 million, concentrated in Maule and Ñuble.

IndicatorFigureSource
Data centers on the CEN's list~20Transmisoras de Chile
In operation~7 (about 350 MW)Transmisoras de Chile
In the connection process6Transmisoras de Chile
Rejected requests on hold6 (1,420 MW)CEN via La Tercera
Transmission works on schedule~30%Transmisoras de Chile
Pending transmission investment~US$2 billionUniversity of Chile study

Data centers in Chile: demand that keeps growing

The pressure comes from artificial intelligence and the cloud. The DC SC2 request alone exceeds all the data center capacity connected in Chile between 2020 and May 2026, which according to DCD totaled about 407 MW, as reported by TransMedia. That project estimated consumption of about 4 TWh a year and commercial operation in September 2030.

Long-term planning already factors in this jump. In the electricity demand projection to 2046, data centers appear alongside mining and green hydrogen among the drivers that could nearly double the country's consumption.

Some projects have found specific solutions. The Panel of Experts, for example, backed the Coordinator in the Huechuraba data center case, which will connect with a single authorization. But the industry warns that the lack of capacity repeats in Lampa, Colina, Tiltil and Pudahuel, precisely the municipalities with large plots of land near Santiago.

Average outage hours per customer per year (SAIDI)
Source: Figures cited by La Tercera
View the data as a table
202313.58 hours
202427.60 hours
202520.91 hours

A grid with longer outages than three years ago

The interview also reviewed service quality. The SAIDI index, which measures the average hours without power per customer per year, was 13.58 hours in 2023, jumped to 27.6 hours in 2024 and fell to 20.91 hours in 2025, according to the figures cited by La Tercera. "This index is extremely high in Chile," said Tapia, who mentioned towns that depend on a single line, such as Chañaral, and regions with frequent outages such as Antofagasta, Maule and Los Lagos.

The Chilean Data Center Association (ACHDC) did not confirm the Coordinator's figures, but acknowledged that "today the timelines of transmission works do not always match those of new projects". The Ministry of Energy has not publicly commented on the list.

Aerial view of a data center roof covered with cooling equipment
The roof of a data center, full of cooling units. Cooling is a large part of these facilities' electricity use. Photo: Rsparks3 / Wikimedia Commons (CC0).

What comes next for the projects on hold

Rejected projects can apply again when capacity frees up or when the substation and line expansions already included in the Coordinator's and the CNE's expansion plans come into service. Some developers are considering connecting directly to the 500 kV grid or building their own infrastructure, which are costlier and slower options.

  • Waiting list: requests are recorded and reviewed when new capacity becomes available.
  • Pending works: they depend on CNE and Coordinator tenders, which can take five to seven years to materialize.
  • Location: projects could move to areas with more grid headroom, away from northern Santiago.
  • Actual consumption: the 1,420 MW is requested capacity; real consumption will depend on how much gets built.

Redimin clarified that there is no confirmed figure for lost jobs or cancelled investments, and that the case is not directly linked to higher household electricity bills.

Does your company develop data centers, substations or transmission solutions? Reach Energía Futura's readers.

See advertising formats

Frequently asked questions

How many data centers were left without a grid connection?

At least six connection requests, totaling 1,420 MW, were rejected by the Electricity Coordinator and placed on a waiting list.

Where are those projects?

In Tiltil-Polpaico, Lampa, Colina-Chicureo and Buin-Maipo, in the Santiago Metropolitan Region.

Why were they rejected?

Because the substations they wanted to connect to have no room for new connections and the expansion works have not yet been built.

How much power do data centers in Chile use today?

The roughly seven in operation on the Coordinator's list require about 350 MW, according to Transmisoras de Chile.

Does this affect electricity bills?

Not directly. The sources do not link the rejections to higher household tariffs.