LATESTChile's 2026 tailings registerSQM earns US$1.569 billion through September, up 288% on lithium, but expects lower pricesMetro and Transelec prepare the Cerro Navia substation that will power Santiago's Lines 7, 9 and AEcoVera Territorium proposes a US$800 million plant to turn Santiago's waste into 800 GWh of electricity
ENERGÍA FUTURA
Solar Energy

Chile's grid operator identifies 261 small distributed plants whose exit would put supply at risk: they total 1,280 MW

By ·

Chile's grid operator identifies 261 small distributed plants whose exit would put supply at risk: they total 1,280 MW

Chile's National Electricity Coordinator has identified 261 small distributed generation plants (PMGD), with combined capacity of 1,280.09 MW, whose withdrawal could affect the operational security of the National Electric System. Another 17 plants, with 43.91 MW, play a key role in restoring supply after transmission failures. The analysis is in Security Report GO No. 25/2026, which the grid operator sent to the National Energy Commission (CNE) and which became public on Tuesday 17 November.

The study reviewed 830 PMGD installations that, as of September 2026, totalled 3,765.49 MW between Arica and Chiloé. The 261 critical plants account for about 34% of that capacity, and the 17 restoration plants for about 1%, according to REDIMIN.

The small plants the grid cannot lose
261PMGD critical for securityOut of 830 analysed
1,280.09 MWCapacity of those 261About 34% of all PMGD capacity
17Key to restoring serviceTotal 43.91 MW
3,765.49 MWTotal PMGD capacityAs of September 2026
Source: National Electricity Coordinator, Security Report GO No. 25/2026, via REDIMIN, 17 Nov 2026
View the data as a table
PMGD critical for security261
Capacity of those 2611,280.09 MW
Key to restoring service17
Total PMGD capacity3,765.49 MW

What PMGD plants are and why the grid operator reviews their exit

PMGD are plants of up to 9 MW connected to medium-voltage distribution networks. Most are small solar plants, although there are also mini-hydro, wind and thermal units. They have a special price regime, the stabilised price, which the CNE has just recalculated: under the new formula, midday energy is worth almost nothing, as we explained in our story on PMGD stabilised prices.

Supreme Decree No. 88 of 2019, which regulates these plants, requires in Article 104 a 24-month notice for any withdrawal, disconnection or shutdown. Article 106 allows the CNE, in qualified cases and after a security report from the Coordinator, to exempt a company from that deadline. For that, the Coordinator must tell the CNE which facilities can withdraw without putting the system at risk, according to the text of the regulation.

Report categoryPlantsCapacityWhat it means
Critical for security2611,280.09 MWTheir withdrawal could affect system operation
Relevant for restoring service1743.91 MWThey help restore supply after transmission failures
Withdrawal with no negative impact (Annex I)552 (calculated)2,441.49 MW (calculated)Could request early disconnection
Total analysed8303,765.49 MWPMGD between Arica and Chiloé, as of September 2026

Source: National Electricity Coordinator, Security Report GO No. 25/2026, via REDIMIN, 17 November 2026. The third row is obtained by subtracting the first two from the total; the report lists those plants individually in its Annex I.

A third of PMGD capacity is critical to the gridInstalled capacity by report category, MW
The remainder was calculated by subtracting both categories from the 3,765.49 MW total.Source: National Electricity Coordinator, Security Report GO No. 25/2026, via REDIMIN, 17 Nov 2026
View the data as a table
261 critical1,280.09 MW
17 for restoration43.91 MW
552 others2,441.49 MW

The areas where small plants keep the lights on

The first category groups plants connected in areas with transmission constraints or little local generation. There, PMGD output relieves overloads on lines and transformers and supplies demand that would otherwise be exposed. The report names the Charrúa-Parral-Chillán, Linares-Chacahuín-Panimávida and Alto Jahuel-Punta de Cortés-Tinguiririca transmission systems, plus the 110 kV ring of the Santiago Metropolitan Region, and covers facilities in Valparaíso, Maule, Biobío, La Araucanía and Los Lagos.

Transmission system named in the reportRegions
Charrúa-Parral-ChillánBiobío, Ñuble and Maule
Linares-Chacahuín-PanimávidaMaule
Alto Jahuel-Punta de Cortés-TinguiriricaMetropolitana and O'Higgins
110 kV ringMetropolitana (Santiago)
Other facilities consideredValparaíso, La Araucanía and Los Lagos

Source: National Electricity Coordinator, Security Report GO No. 25/2026, via REDIMIN. The regions for each system correspond to the location of its substations.

Where the areas that depend on small plants areSubstations of the transmission systems named in the report
Charrúa-Parral-ChillánLinares-Chacahuín-PanimávidaAlto Jahuel-Punta de Cortés-TinguiriricaSantiago Metropolitan Region
110 kV ringSantiago Metropolitan Region
Alto JahuelAlto Jahuel-Punta de Cortés-Tinguiririca
Punta de CortésAlto Jahuel-Punta de Cortés-Tinguiririca
TinguiriricaAlto Jahuel-Punta de Cortés-Tinguiririca
PanimávidaLinares-Chacahuín-Panimávida
Linares / ChacahuínLinares-Chacahuín-Panimávida
ParralCharrúa-Parral-Chillán
ChillánCharrúa-Parral-Chillán
CharrúaCharrúa-Parral-Chillán
Each point is placed at the substation's town, not its exact coordinates. The report also covers facilities in Valparaíso, La Araucanía and Los Lagos.Source: National Electricity Coordinator, Security Report GO No. 25/2026, via REDIMIN, 17 Nov 2026
View the data as a table
CharrúaCharrúa-Parral-ChillánCabrero, Biobío
ParralCharrúa-Parral-ChillánMaule
ChillánCharrúa-Parral-ChillánÑuble
Linares / ChacahuínLinares-Chacahuín-PanimávidaMaule
PanimávidaLinares-Chacahuín-PanimávidaColbún, Maule
Alto JahuelAlto Jahuel-Punta de Cortés-TinguiriricaBuin, Santiago Metropolitan Region
Punta de CortésAlto Jahuel-Punta de Cortés-TinguiriricaO'Higgins
TinguiriricaAlto Jahuel-Punta de Cortés-TinguiriricaO'Higgins
110 kV ringSantiago Metropolitan RegionSantiago

The second category, of 17 plants, includes PMGD that make it possible to partially or fully restore service when a transmission facility fails permanently, in areas with no backup connection through medium-voltage networks. Several of these areas match those flagged in the Coordinator's diagnosis of the zonal grid to 2034, such as Santiago's 110 kV ring.

High-voltage line in southern Santiago
A high-voltage line in southern Santiago. The Santiago region's 110 kV ring is one of the areas where PMGD help sustain supply. Photo: uribarri / Wikimedia Commons (CC BY-SA 4.0).

Being on the list does not mean closing or staying

The report makes clear that being listed is not an automatic authorisation to stop operating nor a closure order. Plants in Annex I, which are not connected to the substations in the two critical categories, could ask the CNE for an early disconnection without the 24-month notice. The remaining 278 would have to respect the deadline or justify an exception. The CNE has the final say in each case.

Does your company develop, operate or finance PMGD plants? Reach Energía Futura's readers.

See advertising options

The report lands amid the dispute over the 15% cap on PMGD plants

The list comes a week after the 8 November fault, when a failure on the 220 kV Chena-Cerro Navia line at 14:54 caused the loss of about 520 MW of generation, much of it PMGD. Since 10 November, the Coordinator has ordered distribution companies to cap the injection of the affected plants at 15% of their capacity, as we explained in our story on the 15% cap on PMGD.

On Monday 16, the Independent Energy Generators Association (GIE) asked the Coordinator to review and lift that restriction. According to the group, almost all the disconnections were caused by the VVS anti-islanding protection, which detects sudden jumps in the voltage angle, and the projects met current requirements. It recalled that CNE Exempt Resolution No. 412 of 2026 gave them until 19 August 2027 to adjust their protections and questioned the lack of information on how the threshold was set, according to Revista Electricidad.

PMGD: from the 8 November fault to the security report
  1. 8 Nov 2026Chena-Cerro Navia faultAt 14:54 the 220 kV line trips and PMGD disconnect.
  2. 10 Nov 202615% capThe Coordinator caps injection from the affected plants.
  3. 16 Nov 2026GIE asks to lift itThe trade group questions the threshold and its economic impact.
  4. 17 Nov 2026GO 25/2026 report made public261 critical PMGD and 17 relevant for restoring service.
  5. 19 Aug 2027Protection deadlineDeadline under CNE Exempt Res. 412/2026 to adjust protections.
Source: REDIMIN and Revista Electricidad, Nov 2026
High-voltage towers in the desert
High-voltage towers in northern Chile. The Coordinator's report analyses the 830 PMGD installations connected between Arica and Chiloé. Photo: GNZXALO / Wikimedia Commons (CC0).

The system thus faces two pressures at once: small plants that, under the new prices, might seek to exit, and a grid operator that needs a third of that capacity to stay connected to support the grid in areas with insufficient transmission.

Frequently asked questions

What is a PMGD?

A small distributed generation plant (Pequeño Medio de Generación Distribuida): a plant of up to 9 MW connected to the distribution grid. Most in Chile are solar plants.

How many PMGD plants are critical for the system?

261 plants with 1,280.09 MW, according to the Coordinator's Security Report GO No. 25/2026. Another 17, with 43.91 MW, are relevant for restoring service.

Can a PMGD stop operating whenever it wants?

No. Decree 88 requires 24 months' notice. The CNE can waive that deadline for plants whose exit does not affect security, after a report from the Coordinator.

Is the 15% cap on PMGD still in place?

The Coordinator has applied it since 10 November to the plants affected by the 8 November fault. GIE and Grenergy asked for it to be lifted; as of 16 November no change had been reported.