The private lines and substations that connect power plants and mines to Chile's grid have less and less room for new projects. The 2026 Available Technical Capacity Study (ECTD) by the National Electricity Coordinator, released in preliminary form on 20 November, analyses 580 dedicated transmission facilities and finds 100 with under 10 MW available to inject power during the day, against 80 in the 2025 study.
The same report shows who wants that room: in 2025 the Coordinator approved 65 capacity-use requests for 6.4 GW, and 77% were linked to energy storage, with 83% of the capacity. Comments on the study are accepted until 27 November 2026.
View the data as a table
| Dedicated facilities analysed | 580 |
| Under 10 MW to inject by day | 100 |
| Connection requests approved in 2025 | 65 |
| Linked to storage | 77% |
What the available technical capacity study measures
Dedicated transmission systems are the lines and substations that generators or large customers build to connect to the grid. Unlike national and zonal transmission, they are not planned by the state, but article 80 of the General Electricity Services Law requires the Coordinator to publish every year how much capacity they have left. A new project that wants to use that capacity must file a Request for Use of Available Technical Capacity (SUCTD).
The study calculates each facility's available capacity taking into account its design, expected maximum use, signed transmission contracts and declared own projects. It then classifies each into three ranges, up to 10 MW, 10 to 100 MW and over 100 MW, for daytime injection, night-time injection and withdrawal, over a ten-year horizon.
| Indicator | ECTD 2025 | ECTD 2026 |
|---|---|---|
| Facilities with under 10 MW for daytime injection | 80 | 100 |
| Facilities with under 10 MW for night-time injection | 60 | 82 |
| Facilities with under 10 MW for withdrawal (2031) | 37 | 59 |
| Facilities without technical data | n/a | 12 (2%) |
Source: National Electricity Coordinator, 2026 ECTD for dedicated transmission systems, preliminary version, November 2026.
Available technical capacity by day and by night
The study separates day and night because the system behaves differently at each time. During the day, solar plants fill the lines: in the 2027 daytime injection scenario there are 100 facilities with under 10 MW free and 179 with over 100 MW. At night, when batteries do most of the injecting, facilities with under 10 MW fall to 82 and those with over 100 MW rise to 225.
View the data as a table
| Up to 10 MW | 10 to 100 MW | Over 100 MW | |
|---|---|---|---|
| Daytime injection, 2027 | 100 | 289 | 179 |
| Night-time injection, 2027 | 82 | 261 | 225 |
| Withdrawal, 2027 | 47 | 253 | 268 |
| Withdrawal, 2031 | 59 | 242 | 267 |
For withdrawal, meaning room for new consumers such as mines, data centres or hydrogen plants, more than half of the facilities can host large projects: 268 exceed 100 MW in 2027. But those with almost no margin rise from 47 in 2027 to 59 in 2031, against 37 in the previous study. The Coordinator explains that capacity already approved is deducted in full, even if the projects are not yet connected.

The north has more room, but also more full facilities
The study groups facilities into three zones. The north, from Arica y Parinacota to Coquimbo, has 279 of the 568 facilities with data and the most potential for large-scale projects, thanks to infrastructure built for generators and mines. Next come the south, from O'Higgins to Los Lagos, with 196, and the centre, with 93 and the least availability.
View the data as a table
| Up to 10 MW | 10 to 100 MW | Over 100 MW | |
|---|---|---|---|
| North (279) | 41 | 103 | 135 |
| Centre (93) | 11 | 49 | 33 |
| South (196) | 30 | 109 | 57 |
The paradox is that the north now also has the most facilities with under 10 MW, displacing the south, which held that record in 2025. In the 2027 night-time injection scenario, the north has 41 facilities with almost no margin and 135 with more than 100 MW free.
| North | 279 | 30 | 31 | 218 |
| Centre | 93 | 11 | 21 | 61 |
| South | 196 | 52 | 39 | 105 |
Does your company develop batteries, transmission or hybrid projects? Reach Energía Futura's readers.
See advertising optionsBatteries dominate connection requests
The figure that sums up the sector's moment is in the executive summary: of the 65 SUCTDs approved in 2025, 77% were for energy storage systems (SAE), renewable plants with storage (CRCA) or batteries meant to form a CRCA, with 83% of the 6.4 GW approved. Annex 3 also lists 86 additional committed projects, 47% more than in 2025, “mainly driven by energy storage projects”.
The trend matches other Coordinator reports. Its latest competition monitoring showed that batteries on the grid already total 5 GW, almost double the 2.6 GW of January.
Batteries seek to connect where lines already exist, especially next to existing solar plants, to charge by day and discharge at night. That is why they compete for the same room on dedicated facilities in the north. In the overall connection queue, BESS projects make up 62% of the 12,188 MW waiting to enter the system.
| Scenario | Up to 10 MW | 10 to 100 MW | Over 100 MW |
|---|---|---|---|
| Daytime injection, 2027 | 100 | 289 | 179 |
| Night-time injection, 2027 | 82 | 261 | 225 |
| Withdrawal, 2027 | 47 | 253 | 268 |
| Withdrawal, 2031 | 59 | 242 | 267 |
Source: National Electricity Coordinator, ECTD 2026. Number of dedicated facilities in each range of available technical capacity.
For a developer, the study is a first map: it shows which facilities are worth requesting a connection at and where there will probably be no room without new works. But it does not replace case-by-case analysis. Of the 580 facilities, 305 have results derived from processing specific requests, in which the Coordinator reviews each project's updated technical and contractual data.

The 8 November fault: the Coordinator asks for two more weeks
Separately, the Coordinator asked the SEC for a two-week extension to deliver the Fault Analysis Study on 8 November, when the disconnection of the 220 kV Chena-Cerro Navia 2 line made frequency drop to 48.9 Hz and tripped 123 small distributed generators (PMGD), as reported by Electrominería. The proposed new date is 11 December.
The body argued it needs dynamic simulations and to review oscillographic records, protection settings and reports from the owners of the 123 PMGDs. After that fault, the Coordinator capped PMGD injection at 15% in the affected area.
Frequently asked questions
What is available technical capacity?
It is the room left on a dedicated line or substation to connect new generation (injection) or consumption (withdrawal) projects, after deducting expected use, contracts and projects already declared.
How many facilities does the 2026 ECTD cover?
580 dedicated transmission facilities. For 12 (2%), capacity could not be calculated due to missing technical data.
Which zone has the most available capacity?
The north, from Arica y Parinacota to Coquimbo. The centre (Valparaíso and Santiago) has the least room for large-scale projects.
Until when can comments be submitted?
Until 27 November 2026, by email to the Coordinator, using the template published with the study.