Chile's National Electricity Coordinator (Coordinador Eléctrico Nacional, CEN) has warned that 60 sections of zonal transmission lines could exceed their rated capacity by 2034 and that, unless this is solved in time, there is a risk of supply shortfalls in Choapa province, in the Coquimbo Region. The warning comes in the 2027 Expected Use of the Transmission System Diagnosis, which the grid operator published on 16 November 2026 and which is open for comments until Monday 23 November.
The 92-page report reviews 1,105 zonal line sections through 2034. Of these, 36 would be loaded at 85% to 99% and another 60 would go above 100%. In addition, 10 HV/HV transformers and 44 HV/MV transformers at distribution substations could run overloaded, according to the Coordinator's diagnosis report.
View the data as a table
| Line sections over capacity | 60 |
| Sections at 85% to 99% | 36 |
| HV/HV transformers over 100% | 10 |
| HV/MV transformers over 100% | 44 |
What the Coordinator's transmission diagnosis says
The diagnosis is the first step in the yearly transmission planning process set by Article 91 of Chile's General Electricity Services Law. With it, the Coordinator shows where the grid will become congested in coming years; with comments from companies and the public, it then drafts the expansion proposal it must submit to the National Energy Commission (CNE) within the first 15 days of January 2027. The CNE decides which works are tendered.
The analysis is based on the 2026-2046 Long-Term Demand Projection and the 2025-2045 Generation Works Plan. It splits the system into six zones (from Arica to Chiloé) and reviews both the national grid and the zonal lines and transformers that carry power to cities. The Coordinator's release stresses that the study already includes new high-consumption loads such as data centres.
| Zonal facilities by 2034 | Total reviewed | Loading 85% to 100% | Loading above 100% |
|---|---|---|---|
| Line sections | 1,105 | 36 (85% to 99%) | 60 |
| HV/MV transformers (distribution) | 790 | 82 | 44 |
| HV/HV transformers | Not given in the summary | Not given in the summary | 10 |
Source: National Electricity Coordinator, 2027 Expected Use of the Transmission System Diagnosis (executive summary), November 2026.
Choapa, Malloco, Maule and Temuco: where the supply risk lies
The most delicate case is the 1x110 kV Choapa-Illapel line. It has an expansion project that the CNE left conditioned in Official Letter No. 507/2026, and while that condition remains unresolved, the Coordinator says, "there could be a risk of not supplying the demand of Choapa province", which includes the towns of Illapel, Salamanca, Los Vilos and Canela.
The report names three other areas with a high probability of not being able to meet all demand: the area around the Malloco substation (Peñaflor), because of the loading of the 1x110 kV Malloco-San Bernardo line, which would reach 166% of its capacity in 2034; the 66 kV system between Itahue and Maule, in the Maule Region; and the 66 kV Pumahue-Chivilcán-Las Encinas network in Temuco. In all of them, the fix depends on new works, load transfers within distribution networks and the success of the tenders that asset owners must run, under CNE Exempt Resolution No. 98/2025 and Official Letter No. 912/2025.
View the data as a table
| Choapa-Illapel 110 kV line | Supply risk | Upgrade conditioned by the CNE (Official Letter 507/2026) |
| Malloco-San Bernardo 110 kV line | Supply risk | 166% loading by 2034 |
| Itahue-Maule 66 kV system | Supply risk | |
| Pumahue-Chivilcán-Las Encinas 66 kV grid | Supply risk | Pumahue-Chivilcán at 113% |
| TR10 Pan de Azúcar 60 MVA | Transformer above 100% | |
| TR4 Ovalle 60 MVA | Transformer above 100% | |
| TR1 Alto Jahuel 30 MVA | Transformer above 100% | |
| TR1 Rancagua 30 MVA | Transformer above 100% | |
| TR2 y TR3 San Fernando (25 y 56 MVA) | Transformer above 100% | |
| TR3 Chillán 75 MVA | Transformer above 100% | |
| TR2 Los Ángeles 75 MVA | Transformer above 100% | 106% |
| TR Lastarria 75 MVA | Transformer above 100% | 108% |
| TR4 Valdivia 60 MVA | Transformer above 100% | 108% |

The most overloaded lines in the transmission system by 2034
Zone by zone, the report gives the projected loading for 2034. In the Santiago Metropolitan Region there are nine 110 kV circuits with problems: besides Malloco-San Bernardo, they include Tap Libertadores-Punta Verde (up to 131%), Tap Libertadores-Lo Campino (126%) and Tap La Reina-Baja Cordillera (115%). In the Diego de Almagro-Quillota zone, the Totoralillo-Tap Los Maquis sections reach 131%.
In the south, constraints are concentrated in the 66 kV networks that supply Concepción, Los Ángeles and Temuco. The 2x66 kV Lastarria-Loncoche line would reach 126%, Pitrufquén-Licanco 128%, Los Ángeles-Manso de Velasco 113% and, around Temuco, Pumahue-Chivilcán 113% and Temuco-Pumahue 110%.
| Zonal line | Zone | Projected loading in 2034 |
|---|---|---|
| 1x110 kV San Bernardo-Malloco | Metropolitan | 166% |
| Tap Libertadores-Punta Verde 110 kV C2 | Metropolitan | 131% |
| Totoralillo-Tap Los Maquis 110 kV C2 | Diego de Almagro-Quillota | 131% |
| 1x66 kV Pitrufquén-Licanco C2 | Charrúa-Chiloé | 128% |
| 2x66 kV Lastarria-Loncoche (C1 and C2) | Charrúa-Chiloé | 126% |
| Tap Libertadores-Lo Campino 110 kV C1 | Metropolitan | 126% |
| Los Villares-Tap Los Maquis 110 kV C1 | Diego de Almagro-Quillota | 121% |
| Tap La Reina-Baja Cordillera 110 kV L2 | Metropolitan | 115% |
| 1x66 kV Los Ángeles-Manso de Velasco | Charrúa-Chiloé | 113% |
| 1x66 kV Pumahue-Chivilcán | Charrúa-Chiloé | 113% |
Source: National Electricity Coordinator, 2027 Diagnosis, zonal transmission chapters. For the Metropolitan Region, the base spring-summer daytime scenario is shown; in the scenario without the Renca project some values change (for example, Tap La Reina-Baja Cordillera rises to 125%).
Does your company build, operate or supply the transmission grid? Reach Energía Futura's readers.
See advertising optionsTen transformers would go above 100% of their capacity
The diagnosis identifies 10 HV/HV transformers that could exceed 100% of their capacity by 2034, from Coquimbo to Los Ríos. The Coordinator attributes this to organic demand growth and high reactive power requirements, especially in the stretch between Alto Jahuel and Charrúa.
| TR10 Pan de Azúcar | 110/69/13,8 kV | 60 MVA | Coquimbo |
| TR4 Ovalle | 110/66/23 kV | 60 MVA | Coquimbo |
| TR1 Alto Jahuel | 110/69/13,8 kV | 30 MVA | Metropolitana |
| TR1 Rancagua | 154/69/14,8 kV | 30 MVA | O'Higgins |
| TR2 San Fernando | 154/69/14,8 kV | 25 MVA | O'Higgins |
| TR3 San Fernando | 154/69/14,8 kV | 56 MVA | O'Higgins |
| TR3 Chillán | 154/66 kV | 75 MVA | Ñuble |
| TR2 Los Ángeles | 154/66/14,8 kV | 75 MVA | Biobío |
| TR Lastarria | 220/66/13,2 kV | 75 MVA | La Araucanía |
| TR4 Valdivia | 230/69/13,8 kV | 60 MVA | Los Ríos |
Among the 790 HV/MV transformers at primary distribution substations, 82 would be loaded at 85% to 100% and 44 above 100%. The report notes that in several cases the result depends on the load transfers distributors can make and on new substations and transformers being commissioned.
The national grid: Kimal-Lo Aguirre, Santiago and Biobío wind
On the backbone grid, the Coordinator projects that the Norte Grande would hold between 49% and 65% of the system's installed capacity by 2047, mostly solar PV and batteries (BESS). That increases use of the Kimal-Lo Aguirre direct-current line, due in 2029 and now under construction, as we reported in our story on Kimal-Lo Aguirre's progress. Because batteries discharge at night, north-to-centre transfers also stretch into night-time hours.
The Central zone shows "recurring" constraints: congestion in the 500/220 kV transformers at Polpaico, Lo Aguirre and Alto Jahuel and in the 220 kV system of north-western Santiago, due to the Polpaico-Cerro Navia section. The report also warns that scaling back the capacity upgrade of the 2x500 kV Alto Jahuel-Lo Aguirre line from 3,000 to 1,950 MVA would cause congestion in the long term. In the South, wind growth in Biobío would congest the 220 kV Charrúa-Mulchén section and the Digüeñes substation.
To connect north, centre and south, the study assessed interregional options and kept two for further analysis: a 1,500 MVA alternating-current line near Charrúa and Lo Aguirre around 2038, and a 2,000 MW direct-current line between the areas of Jadresic and Lo Aguirre around 2042.
- 16 Nov 2026Diagnosis published
- 23 Nov 2026Comments close
- January 2027Expansion proposal to the CNE
- 2029Kimal-Lo Aguirre HVDC line enters service
- 2034Zonal diagnosis horizon60 sections over capacity without new works.
- 2038Charrúa-Lo Aguirre HVAC option1,500 MVA
- 2042Jadresic-Lo Aguirre HVDC option2,000 MW

The demand behind the diagnosis: up to 165 TWh in 2046
The diagnosis uses three demand scenarios. In 2026 projected consumption is between 81.9 and 83.4 TWh; by 2046 it reaches 134.2 TWh in the low scenario, 147.3 TWh in the medium one and 165.8 TWh in the high one, with annual growth of 2.5%, 2.9% and 3.5%. By 2046, distribution customers would account for about 55% of demand, large copper mining for 24% to 26% and green hydrogen for 8% to 11%. The details are in our story on demand that could almost double by 2046.
That demand pressure is already visible in Santiago's grid. The Coordinator warns that structural fixes for the Metropolitan Region could be limited by the lack of physical space at substations, a problem made worse by the growing number of connection requests from batteries, solar plants and data centres. It is the same bottleneck that left six data centres totalling 1,420 MW on a waiting list.
What comes next: comments until 23 November and a proposal in January
Companies, developers, consultants and anyone else can send comments on the diagnosis until Monday 23 November, using the template the Coordinator posted on its website. With that input, the operator will prepare the 2027 Transmission Expansion Proposal, due at the CNE in January 2027. The works the CNE includes in its plan are tendered afterwards; the latest tender for new works, for example, awarded 17 projects for US$475 million in early November.
The report also ran a sensitivity test on what happens if already-decreed works with execution or tendering problems are delayed or dropped. In the Central and Southern zones the effect would be local, but dropping the capacity upgrade of the 2x220 kV Ciruelos-Cautín line could keep in place, over the long term, congestion that is already visible today.
Frequently asked questions
What is the Coordinator's transmission diagnosis?
It is a yearly report that projects the use of the power system's lines and transformers over the next 20 years and identifies where congestion or overloads will occur. It underpins the new-works proposal the Coordinator sends to the CNE every January.
Will there be power cuts in Choapa?
The report does not announce outages. It warns that unless the condition the CNE placed on the Choapa-Illapel line upgrade is resolved, the province's full demand might not be met by 2034.
How many zonal lines would exceed their capacity?
Of 1,105 line sections reviewed, 60 would go above 100% of their rated capacity by 2034 and another 36 would sit between 85% and 99%.
Until when can comments be submitted?
Until Monday 23 November 2026, using the comments template in the transmission development section of the Coordinator's website.