LATESTChile transmission tender awards 17 projects worth US$475 millionLatin America passes one million electric cars and Chile leads in buses with 5,059 and in chargers per vehicleChile's competition regulator clears AZA's purchase of Huachipato steel assets to make green steel from scrapTranselec places UF 6 million in 25-year bonds with demand at 2.3 times the amount
ENERGÍA FUTURA
Sustainability & ESG

Enel Generación takes its 2027 spot market guarantees to Chile's Panel of Experts, a rise of over 58 billion pesos

By ·

Enel Generación takes its 2027 spot market guarantees to Chile's Panel of Experts, a rise of over 58 billion pesos

Enel Generación Chile took to the power sector's Panel of Experts the calculation with which the Coordinador Eléctrico Nacional, the grid operator, set the financial guarantees it must post to trade on the spot market in 2027. The discrepancy, published as number 35-2026 on October 29, targets a new capacity component that, according to the company, would raise its guarantees by more than CLP 58 billion, REDIMIN reported on October 30.

This is not a fine, an unpaid debt or a payment already made: it is the amount the company must back with financial instruments to cover its obligations in transfers between generators. Guarantees are due at the end of November 2026, so the Panel's ruling faces a tight deadline.

The Panel of Experts is an autonomous body that settles disputes between power companies and sector authorities, and its rulings are binding within its remit. At the time of writing, there was no ruling on the merits.

What spot market guarantees are

In Chile, generators sell power to their customers under contract, but physical output is decided by the grid operator according to each plant's cost. So every month some generators buy energy from others on the spot market and others sell. If a company does not pay its balances, the problem spreads along the whole payment chain.

In January 2023, after several payment defaults by small companies, the National Energy Commission (CNE) proposed reforms to strengthen that market. One response came with the Energy Ministry's Supreme Decree No. 32, published in the Official Gazette on June 17, 2026, which amended the system coordination and operation regulation, including articles 156 and 157 on guarantees.

Before DS 32With DS 32
Guarantees covered only energy transfersThey cover energy and capacity
Calculated under the coordination and operation technical standardBacking of at least three months of billing
—Uses the three months of greatest deficit in projected scenarios
—Capacity is valued at short-term node prices

Source: DS 32 of 2026 and the grid operator's calculation, as described by REDIMIN. Sufficiency capacity is the payment plants receive for being available to cover peak demand, even if they do not generate.

Timeline of the 2027 guarantees calculation

DateMilestone
June 17, 2026DS 32 published in the Official Gazette
September 3, 2026Grid operator publishes the preliminary calculation of 2027 guarantees
September 16, 2026Grid operator publishes a preliminary internal procedure on payment-chain compliance, still open to comments
October 2, 2026Grid operator publishes the final calculation
October 29, 2026Panel publishes Enel Generación's discrepancy 35-2026
End of November 2026Deadline to post the guarantees

Source: REDIMIN, based on documents from the grid operator, the Panel of Experts and the Official Gazette.

Enel Generación's dispute over 2027 guarantees

CLP 58 billion

Guarantee increase claimed by Enel

Due to the new capacity component

3

Months of billing to back

Energy and capacity, under DS 32

35

Discrepancy number

Published on October 29, 2026

Source: REDIMIN, October 30, 2026

View the data as a table
Guarantee increase claimed by EnelCLP 58 billion · Due to the new capacity component
Months of billing to back3 · Energy and capacity, under DS 32
Discrepancy number35 · Published on October 29, 2026

What Enel Generación is disputing

Enel Generación does not dispute that capacity guarantees exist: DS 32 establishes them. Its argument is that the grid operator applied that component to the 2027 annual calculation before the CNE issued the final technical standard that must specify how it is calculated. According to the company, the grid operator's September internal procedure was still open to comments and does not replace the CNE standard.

The Panel must decide whether including capacity in the 2027 calculation complies with the current framework, including the DS 32 changes and applicable technical standards, and whether the calculation should stand or be modified. The grid operator, for its part, has argued in other cases that it simply applies current regulation.

Spillway of the Ralco dam discharging water down the concrete wall
The spillway of the Ralco plant in Alto Biobío, Chile's largest hydroelectric plant and one of Enel Generación's assets. Photo: Ignaciomorgan / Wikimedia Commons (CC BY-SA 4.0).

Enel Generación is one of Chile's largest generators, with hydro plants such as Ralco (690 MW) and Pangue, plus solar, wind and gas plants. Because it runs many plants with supply contracts, its monthly spot market balances are large, which is why the capacity component weighs so heavily in its case. REDIMIN does not report whether other companies raised similar objections or the total impact on the market.

High-voltage towers and power lines in Chile
Transmission lines in Chile. Energy and capacity transfers between generators are settled every month on the spot market run by the grid operator. Photo: ShootingStarMax / Wikimedia Commons (CC BY-SA 4.0).

The guarantees do not raise electricity bills

The dispute does not, by itself, imply higher household tariffs or a change in energy prices. Guarantees are a financial backstop between companies, and each generator bears its cost. What is at stake is how much capital generators must tie up to take part in the market and how well protected the payment chain is if someone does not pay.

It is not the first time this year the Panel has ruled on the grid operator's rules. In October it backed the grid operator on the connection of a data center in Huechuraba, a case we covered in our story on the Huechuraba data center.

The same DS 32 is behind another debate: how the grid operator dispatches batteries, which we analyzed in our story on battery dispatch and DS 32. The decree set deadlines to adjust those rules, and the guarantees dispute shows that its application still creates differences between companies and the grid operator.

Meanwhile, the grid operator reported to the SEC that five companies owed public service charge payments, another sign that the sector's payment chain remains under scrutiny. We covered it in our story on the debts reported to the SEC.

Does your company advise generators on regulation or finance? Reach Energía Futura's readers.

See advertising options

Frequently asked questions about Enel Generación's guarantees

Does Enel Generación have to pay CLP 58 billion?

No. It is the increase in guarantees the company estimates from the new capacity component: a financial backstop, not a payment or a fine.

What is the Panel of Experts?

An autonomous body created by Chile's General Electricity Services Law that settles disputes between companies and sector authorities. Its rulings are binding.

When will the Panel rule?

There is no public date. The 2027 guarantees must be posted at the end of November 2026.

Does this affect electricity bills?

Not directly. Guarantees are a backstop between spot market companies and are not part of regulated tariffs.