LATESTChile's 2026 tailings registerSQM earns US$1.569 billion through September, up 288% on lithium, but expects lower pricesMetro and Transelec prepare the Cerro Navia substation that will power Santiago's Lines 7, 9 and AEcoVera Territorium proposes a US$800 million plant to turn Santiago's waste into 800 GWh of electricity
ENERGÍA FUTURA
Sustainability & ESG

Locating new data centres in southern Chile would save the power system US$112 million, Vinken says

By ·

Locating new data centres in southern Chile would save the power system US$112 million, Vinken says

If the new data centres expected in Chile were built in the south instead of the central zone, the power system would save US$112 million in present value, equal to 6.3% of the cost of supplying that load. That is the conclusion of a study by consultancy Vinken, carried out with support from Reset Network and the Environmental Defense Fund (EDF), presented by its director Matías Negrete and published by REDIMIN on 13 November.

The exercise starts from the 647 MW of new data-centre demand that the Energy Ministry's Long-Term Energy Planning (PELP) projects toward 2050, and compares two locations: the south and the central zone, where the industry is concentrated today. The reason for the savings, Negrete says, is that southern wind generates at night and can match the round-the-clock consumption of data centres.

Data centres in the south, in figures
647 MWDemand analysedPELP, toward 2050
US$112 millionSystem savings6.3% of the cost; present value
1.4 GWLess storageWith similar generation
Source: Vinken, Reset Network and EDF, via REDIMIN, 13 Nov 2026
View the data as a table
Demand analysed647 MW
System savingsUS$112 million
Less storage1.4 GW

How much data centres in the south would save

The US$112 million in savings includes about US$30 million in lower transmission investment; the figures do not add up, as the second is part of the first. The study also estimates that a southern location would reduce the storage capacity that has to be installed by about 1.4 GW, with similar generation capacity in both scenarios.

Vinken study resultValueWhat it means
Data-centre demand analysed647 MWPELP projection toward 2050
Savings for the power systemUS$112 millionPresent value; 6.3% of the cost of adding that load
Transmission savingsUS$30 millionIncluded in the US$112 million
Less storage required~1.4 GWWith similar generation
Time to build a data centre1 to 3 years
Time to build transmission7 to 10 years

Source: Vinken study with Reset Network and EDF, via REDIMIN, 13 November 2026.

How much of the savings comes from transmissionEstimated savings in present value, US$ million
The US$30 million in transmission is part of the US$112 million; they do not add up.Source: Vinken, Reset Network and EDF, via REDIMIN, 13 Nov 2026
View the data as a table
Total system savingsUS$112
Of which, transmissionUS$30

The study has limits that REDIMIN's report spells out: the model only considers power-system costs. It leaves out water availability, land use, local impacts, companies' private costs, fibre-optic connectivity, latency and labour. That is why, it says, the result does not prove the south is better in overall economic terms: it shows it is better for the grid.

The transmission sections that would change

The transmission savings are concentrated in the south-centre corridor, which today carries Biobío's power to Santiago. The study identifies two sections whose expansion could be reduced or deferred if part of the demand is located in the south: Mulchén-Nueva Charrúa, in the Biobío Region, and Alto Jahuel-Ancoa, between the Santiago Metropolitan Region and Maule.

The south-centre corridor that would change with data centres in the southSubstations of the two sections Vinken identified and current data-centre hubs
Mulchén-Nueva Charrúa sectionAlto Jahuel-Ancoa sectionData-centre hub
HuechurabaData-centre hub
QuilicuraData-centre hub
S/E Alto JahuelAlto Jahuel-Ancoa section
Ancoa substation (Linares)Alto Jahuel-Ancoa section
Nueva Charrúa substation (Cabrero)Mulchén-Nueva Charrúa section
S/E MulchénMulchén-Nueva Charrúa section
Placed by town, not each substation's exact coordinates. Ancoa substation is shown at Linares.Source: Vinken, Reset Network and EDF, via REDIMIN, 13 Nov 2026
View the data as a table
S/E MulchénMulchén-Nueva Charrúa section
Nueva Charrúa substation (Cabrero)Mulchén-Nueva Charrúa section
Ancoa substation (Linares)Alto Jahuel-Ancoa section
S/E Alto JahuelAlto Jahuel-Ancoa section
QuilicuraData-centre hub
HuechurabaData-centre hub
The Mulchén river in the Biobío Region
The Mulchén river, in the Biobío Region. The Mulchén-Nueva Charrúa transmission section is one of the two whose expansion could change if part of the data-centre demand is located in the south. Photo: LuisCG11 / Wikimedia Commons (CC BY-SA 4.0).

That corridor is precisely the one the National Electricity Coordinator flags as critical in its latest diagnosis: wind growth in Biobío would congest the 220 kV Charrúa-Mulchén section, and the operator is assessing a new 1,500 MVA line between Charrúa and Lo Aguirre around 2038. The difference in timelines matters: a data centre is built in 1 to 3 years, while the transmission it needs takes 7 to 10 years.

Cooling equipment on the roof of a data centre
Cooling equipment on the roof of a data centre. Vinken's study does not include water or climate in its model, only power-system costs. Photo: Rsparks3 / Wikimedia Commons (CC0).

Does your company build data centres or sell them power? Reach Energía Futura's readers.

See advertising options

Why data centres are built in Santiago today

The industry clusters in the Metropolitan Region because of proximity to customers, fibre optics and latency. But the capital's grid is at its limit: six projects totalling 1,420 MW are on a waiting list for lack of transmission capacity, as we reported in our story on the data centres that cannot connect.

In the case of a 20 MW data centre in Huechuraba, the connection went all the way to the Panel of Experts, which backed the Coordinator, as we reported in the dispute over its connection. And the Coordinator warns that the lack of physical space at Santiago's substations could limit fixes for the region, with more and more connection requests from batteries, solar plants and data centres.

The data-centre demand the grid is waiting forMW
These figures differ in nature: a long-term projection versus current connection requests.Source: Vinken, Reset Network and EDF, via REDIMIN, 13 Nov 2026; National Electricity Coordinator
View the data as a table
Six projects on the waiting list (Santiago)1,420 MW
New demand projected in the PELP to 2050647 MW
Huechuraba data centre20 MW

To put the figure in context: the National Electricity Coordinator, in its long-term demand projection, estimates that Chilean data centres' power consumption will rise from about 0.9 TWh in 2025 to between 3.66 and 4.13 TWh in 2046. The PELP's 647 MW, running all year at full load around the clock, would equal about 5.7 TWh, a theoretical ceiling that real data centres do not reach, since they run below their maximum power most of the time.

The National Data Centre Plan and decentralisation

Vinken's proposal intersects with the National Data Centre Plan of the Ministry of Science, Technology, Knowledge and Innovation, which seeks a more sustainable and decentralised development of the industry. The study puts a number on that debate: how much it would cost the power system to keep concentrating demand in the centre versus moving it to where there is surplus power at night.

Data-centre demand is one of the main drivers of the country's consumption projections, alongside mining and green hydrogen. The Coordinator's highest scenario takes power demand to 165.8 TWh in 2046, as explained in our story on demand that could almost double.

Frequently asked questions

How much would the system save if data centres were built in the south?

US$112 million in present value, according to Vinken, equal to 6.3% of the cost of adding 647 MW of data-centre demand. Of that, US$30 million is lower transmission investment.

Why the south?

Because southern wind produces power at night and can match data centres' continuous consumption, reducing the need for batteries and for lines to the centre.

Does the study consider water and fibre optics?

No. It only models power-system costs; it leaves out water, land use, fibre optics, latency, private costs and labour.

How many MW of data centres are projected in Chile?

Long-Term Energy Planning projects 647 MW of new data-centre demand toward 2050. On top of that, six projects totalling 1,420 MW are currently waiting to connect in the Santiago Metropolitan Region.

Who carried out the study?

Consultancy Vinken, with support from Reset Network and the Environmental Defense Fund (EDF). Its director, Matías Negrete, presented it.