If the new data centres expected in Chile were built in the south instead of the central zone, the power system would save US$112 million in present value, equal to 6.3% of the cost of supplying that load. That is the conclusion of a study by consultancy Vinken, carried out with support from Reset Network and the Environmental Defense Fund (EDF), presented by its director Matías Negrete and published by REDIMIN on 13 November.
The exercise starts from the 647 MW of new data-centre demand that the Energy Ministry's Long-Term Energy Planning (PELP) projects toward 2050, and compares two locations: the south and the central zone, where the industry is concentrated today. The reason for the savings, Negrete says, is that southern wind generates at night and can match the round-the-clock consumption of data centres.
View the data as a table
| Demand analysed | 647 MW |
| System savings | US$112 million |
| Less storage | 1.4 GW |
How much data centres in the south would save
The US$112 million in savings includes about US$30 million in lower transmission investment; the figures do not add up, as the second is part of the first. The study also estimates that a southern location would reduce the storage capacity that has to be installed by about 1.4 GW, with similar generation capacity in both scenarios.
| Vinken study result | Value | What it means |
|---|---|---|
| Data-centre demand analysed | 647 MW | PELP projection toward 2050 |
| Savings for the power system | US$112 million | Present value; 6.3% of the cost of adding that load |
| Transmission savings | US$30 million | Included in the US$112 million |
| Less storage required | ~1.4 GW | With similar generation |
| Time to build a data centre | 1 to 3 years | |
| Time to build transmission | 7 to 10 years |
Source: Vinken study with Reset Network and EDF, via REDIMIN, 13 November 2026.
The study has limits that REDIMIN's report spells out: the model only considers power-system costs. It leaves out water availability, land use, local impacts, companies' private costs, fibre-optic connectivity, latency and labour. That is why, it says, the result does not prove the south is better in overall economic terms: it shows it is better for the grid.
The transmission sections that would change
The transmission savings are concentrated in the south-centre corridor, which today carries Biobío's power to Santiago. The study identifies two sections whose expansion could be reduced or deferred if part of the demand is located in the south: Mulchén-Nueva Charrúa, in the Biobío Region, and Alto Jahuel-Ancoa, between the Santiago Metropolitan Region and Maule.
View the data as a table
| S/E Mulchén | Mulchén-Nueva Charrúa section | |
| Nueva Charrúa substation (Cabrero) | Mulchén-Nueva Charrúa section | |
| Ancoa substation (Linares) | Alto Jahuel-Ancoa section | |
| S/E Alto Jahuel | Alto Jahuel-Ancoa section | |
| Quilicura | Data-centre hub | |
| Huechuraba | Data-centre hub |

That corridor is precisely the one the National Electricity Coordinator flags as critical in its latest diagnosis: wind growth in Biobío would congest the 220 kV Charrúa-Mulchén section, and the operator is assessing a new 1,500 MVA line between Charrúa and Lo Aguirre around 2038. The difference in timelines matters: a data centre is built in 1 to 3 years, while the transmission it needs takes 7 to 10 years.

Does your company build data centres or sell them power? Reach Energía Futura's readers.
See advertising optionsWhy data centres are built in Santiago today
The industry clusters in the Metropolitan Region because of proximity to customers, fibre optics and latency. But the capital's grid is at its limit: six projects totalling 1,420 MW are on a waiting list for lack of transmission capacity, as we reported in our story on the data centres that cannot connect.
In the case of a 20 MW data centre in Huechuraba, the connection went all the way to the Panel of Experts, which backed the Coordinator, as we reported in the dispute over its connection. And the Coordinator warns that the lack of physical space at Santiago's substations could limit fixes for the region, with more and more connection requests from batteries, solar plants and data centres.
To put the figure in context: the National Electricity Coordinator, in its long-term demand projection, estimates that Chilean data centres' power consumption will rise from about 0.9 TWh in 2025 to between 3.66 and 4.13 TWh in 2046. The PELP's 647 MW, running all year at full load around the clock, would equal about 5.7 TWh, a theoretical ceiling that real data centres do not reach, since they run below their maximum power most of the time.
The National Data Centre Plan and decentralisation
Vinken's proposal intersects with the National Data Centre Plan of the Ministry of Science, Technology, Knowledge and Innovation, which seeks a more sustainable and decentralised development of the industry. The study puts a number on that debate: how much it would cost the power system to keep concentrating demand in the centre versus moving it to where there is surplus power at night.
Data-centre demand is one of the main drivers of the country's consumption projections, alongside mining and green hydrogen. The Coordinator's highest scenario takes power demand to 165.8 TWh in 2046, as explained in our story on demand that could almost double.
Frequently asked questions
How much would the system save if data centres were built in the south?
US$112 million in present value, according to Vinken, equal to 6.3% of the cost of adding 647 MW of data-centre demand. Of that, US$30 million is lower transmission investment.
Why the south?
Because southern wind produces power at night and can match data centres' continuous consumption, reducing the need for batteries and for lines to the centre.
Does the study consider water and fibre optics?
No. It only models power-system costs; it leaves out water, land use, fibre optics, latency, private costs and labour.
How many MW of data centres are projected in Chile?
Long-Term Energy Planning projects 647 MW of new data-centre demand toward 2050. On top of that, six projects totalling 1,420 MW are currently waiting to connect in the Santiago Metropolitan Region.
Who carried out the study?
Consultancy Vinken, with support from Reset Network and the Environmental Defense Fund (EDF). Its director, Matías Negrete, presented it.